6915 1/2 N CALHOUN AVE 91405
Certificate Information: 6915 1/2 N CALHOUN AVE 91405
- Application / Permit
- 25014-20000-00166
- Plan Check / Job No.
- B25VN00796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1) W/ ADDITION & ENTIRELY NEW ROOF FRAMING.
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 1/18/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/29/2025 | APPLICANT |
| Plan Check Approved | 3/14/2025 | HAYATO TSUCHIYA |
| Issued | 3/19/2025 | APPLICANT |
| CofO in Progress | 10/2/2025 | RYAN SALAZAR |
| CofO Issued | 10/7/2025 | RUBEN SALAS |
| Permit Finaled | 10/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 3/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/6/2025 | SAFA JAVANMARDI |
| ZA Case | Cleared | 3/11/2025 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 4/8/2025 | Conditional Approval | RAUL OLAGI |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/11/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 4/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/7/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/7/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/7/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/7/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 5/8/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/8/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 5/8/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/12/2025 | Approved | RYAN SALAZAR |
| Final | 8/21/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 8/21/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 8/21/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 8/21/2025 | Approved | RYAN SALAZAR |
| Final | 10/3/2025 | OK to Issue CofO | RYAN SALAZAR |