22122 W COVELLO ST 91303

Certificate Information: 22122 W COVELLO ST 91303

Application / Permit
25014-20000-00165
Plan Check / Job No.
B25VN00792
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to single family dwelling to enlarge bedroom. Remodel kitchen area.
Permit Issued
Issued on 3/31/2025
Issuing Office
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/21/2025 MINA HABILI
Corrections Issued 1/22/2025 MINA HABILI
Plan Check Approved 3/28/2025 RICARDO RAMIREZ
Issued 3/31/2025 APPLICANT
CofO in Progress 9/26/2025 JEFFREY HARTLINE
Permit Finaled 9/30/2025 JOHN JANSON
CofO Issued 9/30/2025 JOHN JANSON
Permit Finaled 9/30/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/5/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/5/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/25/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2025 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/17/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/17/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 4/30/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/2/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/2/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 5/2/2025 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/2/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 5/2/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/7/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 5/7/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/7/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 5/8/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/13/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/13/2025 Approved CHRIS CHRISTENSEN
Shower Pan 5/13/2025 Approved CHRIS CHRISTENSEN
Service/Power Release 6/25/2025 Corrections Issued CHRIS CHRISTENSEN
Service/Power Release 7/16/2025 No Access for Inspection CHRIS CHRISTENSEN
Service/Power Release 7/18/2025 Approved CHRIS CHRISTENSEN
Green Building Final 9/9/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 9/9/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 9/12/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 9/12/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 9/12/2025 Approved JEFFREY HARTLINE
Final 9/19/2025 Partial Approval JEFFREY HARTLINE
Green Building Final 9/19/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 9/23/2025 Approved JEFFREY HARTLINE
HVAC-Final 9/23/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 9/23/2025 Approved JEFFREY HARTLINE
Final 9/25/2025 OK to Issue CofO JEFFREY HARTLINE