7751-7753 N OSTROM AVE 91406
Certificate Information: 7751-7753 N OSTROM AVE 91406
- Application / Permit
- 25014-20000-00163
- Plan Check / Job No.
- B25VN00791
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 20'-10"X19'-7" JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 66333 ADDITION TO EXISTING ONE STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 7/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | VAHAN JIVALAGIAN |
| Corrections Issued | 1/28/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 1/30/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 2/3/2025 | APPLICANT |
| Applicant returned to address corrections | 3/24/2025 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 4/17/2025 | DAWN MC NULTY |
| Plan Check Approved | 4/22/2025 | DAWN MC NULTY |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 7/9/2026 | MICHAEL CORTEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/4/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | CARLOS RAMIREZ |
| Address approval | Cleared | 3/30/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/3/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2025 | Partial Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/2/2025 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/1/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/26/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 11/26/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/26/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/13/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 2/13/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/13/2026 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/3/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/3/2026 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/11/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| Insulation | 3/16/2026 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | KIRK SANDERS |
| Shower Pan | 3/16/2026 | Not Ready for Inspection | KIRK SANDERS |
| Special/Order Compliance | 3/16/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 4/15/2026 | Approved | MICHAEL CORTEZ |
| Pre-Inspection | 6/22/2026 | Partial Inspection | MICHAEL CORTEZ |
| Final | 6/30/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 6/30/2026 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 6/30/2026 | SGSOV Not Required | MICHAEL CORTEZ |
| Smoke Detectors | 6/30/2026 | Corrections Issued | MICHAEL CORTEZ |
| Final | 7/8/2026 | OK to Issue CofO | MICHAEL CORTEZ |
| Smoke Detectors | 7/8/2026 | Approved | MICHAEL CORTEZ |