10680 N ILEX AVE 91331

Certificate Information: 10680 N ILEX AVE 91331

Application / Permit
25014-20000-00152
Plan Check / Job No.
B25VN00691
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-4" X 6'-0" ADDITION TO THE (E) SFD
Permit Issued
Issued on 2/26/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/14/2025 ALEC MOUSAKHANIAN
Corrections Issued 1/14/2025 ALEC MOUSAKHANIAN
Plan Check Approved 2/26/2025 YAQUB MIRZA
Issued 2/26/2025 APPLICANT
CofO in Progress 11/14/2025 NICHOLAS TROWBRIDGE
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/5/2025 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/5/2025 CARLOS RAMIREZ
ZI Cleared 2/21/2025 JASON CHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/18/2025 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 3/19/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/21/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 3/21/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 4/1/2025 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 4/14/2025 Partial Inspection MICHEL ABAJAN
Interior/Exterior Lathing 4/14/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/6/2025 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 5/6/2025 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 5/6/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 5/6/2025 Not Ready for Inspection MICHEL ABAJAN
Insulation 6/3/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 6/10/2025 Approved MICHEL ABAJAN
Green Building Rough 6/10/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 6/10/2025 Approved MICHEL ABAJAN
Sewer 6/10/2025 Approved MICHEL ABAJAN
Drywall Nailing 6/13/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/25/2025 Approved MICHEL ABAJAN
Final 7/25/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 7/25/2025 Approved MICHEL ABAJAN
HVAC-Final 7/25/2025 Approved MICHEL ABAJAN
PLUMBING-Final 7/25/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 7/25/2025 Approved MICHEL ABAJAN
Final 11/13/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved NICHOLAS TROWBRIDGE