11301 W COHASSET ST 91352
Certificate Information: 11301 W COHASSET ST 91352
- Application / Permit
- 25014-20000-00149
- Plan Check / Job No.
- B25VN00667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 86 SF ADDITION TO THE (E) SFD , ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Current Status
- CofO Issued on 11/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 1/13/2025 | LUISANGEL VALENZUELA |
| Issued | 1/15/2025 | APPLICANT |
| CofO in Progress | 10/1/2025 | JOSE AVILA |
| Permit Finaled | 11/7/2025 | RUBEN SALAS |
| CofO Issued | 11/7/2025 | RUBEN SALAS |
| Permit Finaled | 11/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/14/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/25/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 4/3/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 4/23/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 4/29/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 4/29/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/29/2025 | Approved | JOSE AVILA |
| FLOOD-Proofing Certificate | 5/6/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/16/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Shower Pan | 5/16/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 5/22/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 5/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 5/28/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 6/2/2025 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 6/2/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 6/12/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 8/11/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/11/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/11/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/26/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | JOSE AVILA |
| Final | 9/30/2025 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 9/30/2025 | Approved | JOSE AVILA |