9937 N KESTER AVE 91345
Certificate Information: 9937 N KESTER AVE 91345
- Application / Permit
- 25014-20000-00148
- Plan Check / Job No.
- B25VN00651
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/12/2025
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | JESSE ARELLANO |
| Corrections Issued | 1/17/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 1/21/2025 | APPLICANT |
| Plan Check Approved | 2/12/2025 | ALEC MOUSAKHANIAN |
| Issued | 2/12/2025 | APPLICANT |
| CofO in Progress | 6/30/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/22/2025 | LEE GUILBEAUX |
| ZA Case | Cleared | 1/23/2025 | DALIA MOKAYED |
| Address approval | Cleared | 1/24/2025 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 1/24/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/24/2025 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/24/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/6/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/6/2025 | Partial Approval | MICHEL ABAJAN |
| Sewer | 3/7/2025 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 3/10/2025 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/7/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/7/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/15/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/21/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/21/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 6/23/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| Final | 6/27/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/27/2025 | Approved | JENNIFER RABUCHIN |