16843 W RINALDI ST 91344
Certificate Information: 16843 W RINALDI ST 91344
- Application / Permit
- 25014-20000-00143
- Plan Check / Job No.
- B25VN00635
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE ALL BUT 13'-2" OF EXTERIOR WALL AND REBUILD 27' X 47' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/16/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/17/2025 | APPLICANT |
| Plan Check Approved | 2/4/2025 | ALEC MOUSAKHANIAN |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 8/5/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2025 | KEVIN CHUNG |
| Construction near power lines | Cleared | 1/21/2025 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2025 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 1/21/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 1/21/2025 | KEVIN CHUNG |
| Grading Pre-Inspection | Cleared | 1/28/2025 | CHARLES POWELL |
| GPI Written Notices | Cleared | 2/4/2025 | ALEC MOUSAKHANIAN |
| Hold | Cleared | 2/26/2025 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/12/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/20/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 3/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 4/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 4/14/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/14/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/18/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 4/18/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 4/18/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/18/2025 | Partial Approval | CHRISTOPHER ROJAS |
| MERV13>=Rough | 4/18/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/24/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 4/24/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 4/28/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/1/2025 | Approved | LOUIS ESCOTO |
| Sewer | 5/14/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 5/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/16/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 7/22/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/22/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 7/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 7/22/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/22/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Rec and Parks Fee Memo | 7/22/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/28/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 7/28/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/28/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 8/5/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Approved | CHRISTOPHER ROJAS |