16843 W RINALDI ST 91344

Certificate Information: 16843 W RINALDI ST 91344

Application / Permit
25014-20000-00143
Plan Check / Job No.
B25VN00635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ALL BUT 13'-2" OF EXTERIOR WALL AND REBUILD 27' X 47' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 JEROME MAGAT PALMA
Corrections Issued 1/16/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/17/2025 APPLICANT
Plan Check Approved 2/4/2025 ALEC MOUSAKHANIAN
Issued 2/4/2025 APPLICANT
CofO in Progress 8/5/2025 CHRISTOPHER ROJAS
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/21/2025 KEVIN CHUNG
Construction near power lines Cleared 1/21/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/21/2025 KEVIN CHUNG
Roof/Waste drainage to street Cleared 1/21/2025 KEVIN CHUNG
Sewer availability Cleared 1/21/2025 KEVIN CHUNG
Grading Pre-Inspection Cleared 1/28/2025 CHARLES POWELL
GPI Written Notices Cleared 2/4/2025 ALEC MOUSAKHANIAN
Hold Cleared 2/26/2025 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/12/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/12/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 3/20/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 3/20/2025 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/14/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 4/14/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/14/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/18/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/18/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 4/18/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 4/18/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/18/2025 Partial Approval CHRISTOPHER ROJAS
MERV13>=Rough 4/18/2025 Approved CHRISTOPHER ROJAS
Insulation 4/24/2025 Approved LOUIS ESCOTO
Shower Pan 4/24/2025 Approved LOUIS ESCOTO
Drywall Nailing 4/28/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/1/2025 Approved LOUIS ESCOTO
Sewer 5/14/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 5/14/2025 Corrections Issued JENNIFER RABUCHIN
Gas Test 5/16/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 7/22/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/22/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 7/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 7/22/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 7/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 7/22/2025 Approved CHRISTOPHER ROJAS
Verify Rec and Parks Fee Memo 7/22/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/28/2025 Approved CHRISTOPHER ROJAS
Final 7/28/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 7/28/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 7/28/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Final 8/5/2025 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Approved CHRISTOPHER ROJAS