13342 W FRIAR ST 91401
Certificate Information: 13342 W FRIAR ST 91401
- Application / Permit
- 25014-20000-00140
- Plan Check / Job No.
- B25VN00621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING; REMOVE DWELLING EXCEPT FOR 25'-5" WALL/FOUNDATION ON WEST SIDE OF LOT; ADD 58'-4" X 40'-1" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ATTACHED OPEN TRELLIS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | SELLA BENYAMIN |
| Corrections Issued | 1/30/2025 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2025 | STEVEN KIM |
| Plan Check Approved | 5/31/2025 | SELLA BENYAMIN |
| Plan Check Approved | 6/5/2025 | SELLA BENYAMIN |
| Issued | 6/5/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | RAUL OLAGI |
| CofO Issued | 5/12/2026 | RUBEN SALAS |
| Permit Finaled | 5/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/25/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/27/2025 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 7/29/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/30/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 8/11/2025 | Approved | GAREN HAYRAPETYAN |
| Deputy Reinf. Concrete | 8/12/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 10/27/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 10/28/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 11/7/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/3/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Rough | 12/3/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Rough | 12/3/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 12/8/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/8/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/8/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/10/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 12/10/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 12/10/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 12/10/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 12/10/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 12/18/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 12/18/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 12/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Insulation | 12/30/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 1/9/2026 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 1/9/2026 | Approved | LOUIS ESCOTO |
| Shower Pan | 1/9/2026 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 1/15/2026 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 4/2/2026 | Approved | RAUL OLAGI |
| Final | 4/2/2026 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/2/2026 | Approved | RAUL OLAGI |
| HVAC-Final | 4/2/2026 | Approved | RAUL OLAGI |
| PLUMBING-Final | 4/2/2026 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 4/2/2026 | Approved | RAUL OLAGI |
| Final | 4/17/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/17/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/28/2026 | OK to Issue CofO | WAYNE REGESTER |