20350-20352 W ALERION PL 91364
Certificate Information: 20350-20352 W ALERION PL 91364
- Application / Permit
- 25014-20000-00128
- Plan Check / Job No.
- B25VN00547
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SFD TO REMOVE PATIO COVERS, ADDITIONS AND CONVERSION OF (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH CA Govt. Code 65852.2(e)(1)(A) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- CofO Corrected on 5/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | ALFRED RAMIREZ |
| Corrections Issued | 1/27/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 1/31/2025 | STEVEN KIM |
| Applicant returned to address corrections | 3/19/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 4/16/2025 | ALFRED RAMIREZ |
| Issued | 4/16/2025 | APPLICANT |
| CofO in Progress | 3/20/2026 | JOHN HAYES |
| CofO Issued-Status Void | 4/17/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 4/17/2026 | JOHN JANSON |
| Re-Activate Permit | 5/11/2026 | JOHN JANSON |
| Permit Finaled | 5/13/2026 | JOHN JANSON |
| CofO Corrected | 5/13/2026 | JOHN JANSON |
| Permit Finaled | 5/13/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/4/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/5/2025 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 4/16/2025 | ALFRED RAMIREZ |
Contact Information
| Contractor | Boutique Construction; Lic. No.: 1051070-B | , |
| Contractor | Design For Success Inc; Lic. No.: 1051070-B | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/27/2025 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/2/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/9/2025 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Partial Approval | SEAN WIRCH |
| HVAC-Rough | 8/14/2025 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/14/2025 | Approved | JOHN HAYES |
| Special/Order Compliance | 8/14/2025 | Partial Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/25/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 8/25/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 8/25/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 8/29/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/4/2025 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 9/15/2025 | Approved | KRISTEN CAUSEY |
| Insulation | 10/6/2025 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 10/9/2025 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/9/2025 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 10/9/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | JOHN HAYES |
| Green Building Rough | 10/16/2025 | Approved | JOHN HAYES |
| Insulation | 10/16/2025 | Approved | JOHN HAYES |
| Drywall Nailing | 10/24/2025 | Approved | MORRIS JACKSON |
| Final | 1/29/2026 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/29/2026 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/29/2026 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 3/12/2026 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/12/2026 | Corrections Issued | JOHN HAYES |
| HVAC-Final | 3/12/2026 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 3/12/2026 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 3/20/2026 | Approved | JOHN HAYES |
| Final | 3/20/2026 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 3/20/2026 | Approved | JOHN HAYES |
| HVAC-Final | 3/20/2026 | Approved | JOHN HAYES |
| PLUMBING-Final | 3/20/2026 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 3/20/2026 | Approved | JOHN HAYES |
| Smoke Detectors | 3/20/2026 | Approved | JOHN HAYES |