10114-10116 N FORBES AVE 91343

Certificate Information: 10114-10116 N FORBES AVE 91343

Application / Permit
25014-20000-00124
Plan Check / Job No.
B25VN00527
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/26/2025
Issuing Office
Current Status
CofO Issued on 5/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2025 APPLICANT
Assigned to Plan Check Engineer 1/15/2025 GURUNATH NESARAJAH
Corrections Issued 1/16/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 2/6/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 2/10/2025 PINANK PATEL
Plan Check Approved 2/24/2025 PINANK PATEL
Issued 2/26/2025 APPLICANT
Permit Finaled 5/27/2026 DAVID JAMES
CofO Issued 5/27/2026 DAVID JAMES
Permit Finaled 5/27/2026 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 1/18/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/18/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/18/2025 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 2/10/2025 GURUNATH NESARAJAH

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/23/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 6/24/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 6/24/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/27/2025 Approved ARA SINANIAN
Underground Mechanical 6/27/2025 Approved ARA SINANIAN
BUILDING-Rough-Frame 7/30/2025 No Access for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/30/2025 No Access for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 7/30/2025 No Access for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 7/30/2025 No Access for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/30/2025 No Access for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 8/5/2025 Approved ARA SINANIAN
PLUMBING-Rough 8/5/2025 Approved ARA SINANIAN
Shower Pan 8/5/2025 Approved ARA SINANIAN
Wood Frame 8/5/2025 Approved ARA SINANIAN
Insulation 8/14/2025 Approved ARA SINANIAN
Interior/Exterior Lathing 8/14/2025 Approved ARA SINANIAN
Drywall Nailing 8/20/2025 Approved ARA SINANIAN
BUILDING-Rough-Frame 4/29/2026 Approved ARA SINANIAN
Final 4/29/2026 Conditional Approval ARA SINANIAN
Green Building Final 4/29/2026 Approved ARA SINANIAN
Green Building Rough 4/29/2026 Approved ARA SINANIAN
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved ARA SINANIAN
Smoke Detectors 4/29/2026 Approved ARA SINANIAN