6729 N QUAKERTOWN AVE 91306
Certificate Information: 6729 N QUAKERTOWN AVE 91306
- Application / Permit
- 25014-20000-00116
- Plan Check / Job No.
- B25VN00505
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert existing detached 20' x 18' garage to new TWO stories irregular shaped 25' x 23' 1/2" ADU per LAMC 12.22 A.33(b)(1)3. NFPA 13D sprinklers required
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Current Status
- CofO Issued on 7/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | NAREG ATARIAN |
| Corrections Issued | 1/19/2025 | NAREG ATARIAN |
| Quality Review Completed | 1/29/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/16/2025 | NAREG ATARIAN |
| Plan Check Approved | 4/22/2025 | NAREG ATARIAN |
| Issued | 4/24/2025 | APPLICANT |
| CofO in Progress | 6/26/2026 | ALEXANDER HANDY |
| Permit Finaled | 7/23/2026 | JOHN JANSON |
| CofO Issued | 7/23/2026 | JOHN JANSON |
| Permit Finaled | 7/23/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | RYAN CASTRO |
| ZI | Cleared | 1/25/2025 | JAZMIN ROQUE |
| Sewer availability | Cleared | 2/19/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 3/5/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/28/2025 | Partial Approval | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 6/2/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/4/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/3/2025 | Corrections Issued | SCOTT SOBEL |
| Green Building Rough | 7/3/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 7/8/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 8/8/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/28/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 8/28/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/18/2025 | Partial Inspection | KRISTEN CAUSEY |
| Service/Power Release | 9/18/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/23/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/23/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/23/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 9/23/2025 | Approved | ALEXANDER HANDY |
| Insulation | 10/24/2025 | Conditional Approval | ALEXANDER HANDY |
| Drywall Nailing | 10/30/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 10/30/2025 | Approved | ALEXANDER HANDY |
| Final | 6/17/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 6/17/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/17/2026 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 6/17/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/25/2026 | Approved | ALEXANDER HANDY |
| Final | 6/25/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 6/25/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/25/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2026 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 6/25/2026 | Approved | ALEXANDER HANDY |