19256-19258 W NORTHFLEET WAY 91356
Certificate Information: 19256-19258 W NORTHFLEET WAY 91356
- Application / Permit
- 25014-20000-00094
- Plan Check / Job No.
- B24VN27313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW ATTACHED ADU ADDITION TO (E) SFD PER LAMC12.22A.33(c) and(e). ALL WORK PER ENG.
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 1/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2025 | SERGIO MUNIZ |
| Corrections Issued | 1/28/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/24/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/19/2025 | LUISANGEL VALENZUELA |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 12/18/2025 | JOHN KIDWELL |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
| CofO Issued | 1/7/2026 | MICHAEL PELHAM |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 2/13/2025 | DAVID URITA |
| ZA Case | Cleared | 2/13/2025 | DAVID URITA |
| ZA Case | Cleared | 2/13/2025 | DAVID URITA |
| Address approval | Cleared | 3/4/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/4/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/4/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2025 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 3/19/2025 | SERGIO MUNIZ |
| Grading Pre-Inspection | Cleared | 3/19/2025 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/2/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/6/2025 | Approved | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 6/5/2025 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/12/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 6/12/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 6/20/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 6/26/2025 | Not Ready for Inspection | HENRY KIM |
| Shower Pan | 6/26/2025 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 7/2/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 7/2/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 7/2/2025 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | JON MCHUGH |
| Green Building Rough | 7/8/2025 | Approved | JON MCHUGH |
| Insulation | 7/8/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/14/2025 | Approved | JOHN KIDWELL |
| Sewer | 9/23/2025 | Approved | JOHN KIDWELL |
| Final | 9/26/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 9/26/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 9/26/2025 | Approved | JOHN KIDWELL |
| Final | 11/14/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 11/14/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Gas Company | JOHN KIDWELL |
| Final | 12/3/2025 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 12/3/2025 | Approved | JOHN KIDWELL |