11218 W COHASSET ST 91352
Certificate Information: 11218 W COHASSET ST 91352
- Application / Permit
- 25014-20000-00084
- Plan Check / Job No.
- B25VN00403
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GAR W/ ATT REC ROOM TO ACCESSORY DWELLING UNIT AND ADDITION PER LAMC 12.22 A.33(c) AND (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 3/3/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | JESSE ARELLANO |
| Corrections Issued | 1/17/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 1/21/2025 | APPLICANT |
| Applicant returned to address corrections | 2/28/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/3/2025 | MOHAMMAD ESMAILI |
| Issued | 3/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 2/25/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/26/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/24/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 4/30/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 4/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 5/5/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 6/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/10/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 10/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 11/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 2/18/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 3/6/2026 | Approved | ROBERTO PALACIOS-LOPEZ |