11775 N ENCINO AVE 91344
Certificate Information: 11775 N ENCINO AVE 91344
- Application / Permit
- 25014-20000-00070
- Plan Check / Job No.
- B25VN00355
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN REMOVE EXISTING 2134 SF OF SFD EXCEPT FOR 4' OF WALL AND FOUNDATION ON THE NORTHERN SIDE. REBUILD 91'-9" X 63'-5" 1-STORY IRREGULAR SHAPED SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Current Status
- CofO Corrected on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | RAPHAEL ROSAS |
| Corrections Issued | 1/15/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 1/17/2025 | STEVEN KIM |
| Applicant returned to address corrections | 3/5/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/25/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 4/2/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 4/10/2025 | RAPHAEL ROSAS |
| Issued | 4/10/2025 | APPLICANT |
| CofO in Progress | 1/23/2026 | STEVEN BACK |
| Re-Activate Permit | 2/12/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 2/12/2026 | JOHN JANSON |
| CofO Issued-Status Void | 2/12/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
| CofO Corrected | 2/20/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/22/2025 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/24/2025 | MITESH PATEL |
| Distance to fire station | Cleared | 2/3/2025 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 2/3/2025 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 3/14/2025 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 4/2/2025 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 4/2/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 5/14/2025 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 5/15/2025 | Approved | STEVEN BACK |
| METHANE-Barrier | 5/15/2025 | Approved | STEVEN BACK |
| METHANE-Subgrade | 5/15/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 6/26/2025 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 7/15/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 7/21/2025 | Approved | STEVEN BACK |
| Shower Pan | 7/25/2025 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/28/2025 | Corrections Issued | SCOTT SOBEL |
| ELECTRICAL-Rough | 8/1/2025 | Approved | STEVEN BACK |
| Shower Pan | 8/1/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/14/2025 | Partial Approval | STEVEN BACK |
| Underground Mechanical | 8/14/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 8/18/2025 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 8/18/2025 | Not Ready for Inspection | STEVEN BACK |
| METHANE-Rough | 8/18/2025 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 8/18/2025 | Approved | STEVEN BACK |
| Underground Mechanical | 8/20/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | STEVEN BACK |
| Green Building Rough | 8/26/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/26/2025 | Approved | STEVEN BACK |
| METHANE-Rough | 8/26/2025 | Approved | STEVEN BACK |
| Insulation | 8/28/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 9/8/2025 | Approved | STEVEN BACK |
| Final | 12/16/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/16/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 12/16/2025 | Approved | STEVEN BACK |
| Final | 1/23/2026 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 1/23/2026 | Approved | STEVEN BACK |
| Service/Power Release | 1/26/2026 | Approved | STEVEN BACK |