17218 W BRAXTON ST 91344

Certificate Information: 17218 W BRAXTON ST 91344

Application / Permit
25014-20000-00067
Plan Check / Job No.
B25VN00344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND ENTRY AT 1ST FLR (8'-6"X9'-6") & EXPAND MASTER BEDROOM AT 2ND FLR (23'-6"X5'-6") TO (E) 2-STORY SFD W/ ATTACHED GARAGE; REMODEL (E) KITCHEN
Permit Issued
Issued on 2/19/2025
Issuing Office
Valley
Current Status
Issued on 2/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 NILOOFAR MEHRAIN
Corrections Issued 1/20/2025 NILOOFAR MEHRAIN
Quality Review Completed 1/23/2025 RARES BODEA
Plan Check Approved 2/13/2025 NILOOFAR MEHRAIN
Issued 2/19/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/22/2025 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 2/6/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/7/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/3/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/4/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 6/25/2025 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 6/25/2025 Corrections Issued JEFFREY PARD
Green Building Rough 6/25/2025 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 6/25/2025 Approved JEFFREY PARD
PLUMBING-Rough 6/25/2025 Approved JEFFREY PARD
BUILDING-Rough-Frame 8/13/2025 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 8/13/2025 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 8/13/2025 Corrections Issued STEVEN BACK
Deputy Wood Construction 8/18/2025 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved STEVEN BACK
Interior/Exterior Lathing 9/4/2025 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 10/14/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/14/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 10/14/2025 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/17/2025 Approved STEVEN BACK
Green Building Rough 10/17/2025 Approved STEVEN BACK
Insulation 10/31/2025 Approved STEVEN BACK
Drywall Nailing 11/25/2025 Approved STEVEN BACK
Shower Pan 12/5/2025 Approved SEAN WIRCH
Special/Order Compliance 12/5/2025 Corrections Issued SEAN WIRCH
Interior/Exterior Lathing 12/26/2025 Partial Approval STEVEN BACK
Shower Pan 12/26/2025 Approved STEVEN BACK
Interior/Exterior Lathing 3/20/2026 Approved STEVEN BACK