17218 W BRAXTON ST 91344
Certificate Information: 17218 W BRAXTON ST 91344
- Application / Permit
- 25014-20000-00067
- Plan Check / Job No.
- B25VN00344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND ENTRY AT 1ST FLR (8'-6"X9'-6") & EXPAND MASTER BEDROOM AT 2ND FLR (23'-6"X5'-6") TO (E) 2-STORY SFD W/ ATTACHED GARAGE; REMODEL (E) KITCHEN
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Valley
- Current Status
- Issued on 2/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/20/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/23/2025 | RARES BODEA |
| Plan Check Approved | 2/13/2025 | NILOOFAR MEHRAIN |
| Issued | 2/19/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/22/2025 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/3/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/4/2025 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/25/2025 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 6/25/2025 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 6/25/2025 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 6/25/2025 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 6/25/2025 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/13/2025 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/13/2025 | Not Ready for Inspection | STEVEN BACK |
| Special/Order Compliance | 8/13/2025 | Corrections Issued | STEVEN BACK |
| Deputy Wood Construction | 8/18/2025 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 9/4/2025 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 10/14/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/14/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | STEVEN BACK |
| Green Building Rough | 10/17/2025 | Approved | STEVEN BACK |
| Insulation | 10/31/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 11/25/2025 | Approved | STEVEN BACK |
| Shower Pan | 12/5/2025 | Approved | SEAN WIRCH |
| Special/Order Compliance | 12/5/2025 | Corrections Issued | SEAN WIRCH |
| Interior/Exterior Lathing | 12/26/2025 | Partial Approval | STEVEN BACK |
| Shower Pan | 12/26/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/20/2026 | Approved | STEVEN BACK |