19544 W HAMLIN ST 91335

Certificate Information: 19544 W HAMLIN ST 91335

Application / Permit
25014-20000-00063
Plan Check / Job No.
B25VN00315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENSLOSE (E) ATTACHED 14'-7" X 9'-5" PATIO COVER AND REMODEL TO (E) SFD. REMOVE FIRE PLACE AND WALL BETWEEN KITCHEN AND LIVING ROOM. INTERIOR REMODEL TO RELOCATE BEDROOM AND ADD 2 BATHROOMS.
Permit Issued
Issued on 1/31/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/13/2025 JEROME MAGAT PALMA
Corrections Issued 1/14/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/17/2025 APPLICANT
Issued 1/31/2025 APPLICANT
CofO in Progress 9/8/2025 ALEXANDER HANDY
Permit Finaled 10/2/2025 MICHAEL PELHAM
Permit Finaled 10/2/2025 MICHAEL PELHAM
CofO Issued 10/2/2025 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/28/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mobed,, Ashkan; Lic. No.: C92493 23450 KITTREDGE ST      WEST HILLS, CA 91307

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2025 Conditional Approval ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 2/24/2025 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 2/24/2025 Partial Approval JOHN COLEMAN
PLUMBING-Rough 2/24/2025 Not Ready for Inspection JOHN COLEMAN
Wood Frame 2/24/2025 Partial Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 2/27/2025 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 3/4/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 3/6/2025 Partial Approval ALEXANDER HANDY
HVAC-Rough 3/6/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 3/6/2025 Approved ALEXANDER HANDY
Insulation 3/11/2025 Partial Approval ALEXANDER HANDY
Interior/Exterior Lathing 3/11/2025 Partial Approval ALEXANDER HANDY
Shower Pan 3/11/2025 Approved ALEXANDER HANDY
Wood Frame 3/11/2025 Partial Approval ALEXANDER HANDY
Drywall Nailing 3/13/2025 Not Ready for Inspection JUAN ALVARADO
Drywall Nailing 3/17/2025 Partial Approval SCOTT SOBEL
Interior/Exterior Lathing 3/17/2025 Not Ready for Inspection SCOTT SOBEL
Interior/Exterior Lathing 3/19/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 4/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Wood Construction 4/7/2025 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 4/10/2025 Approved SCOTT SOBEL
HVAC-Rough 4/10/2025 Partial Approval SCOTT SOBEL
Interior/Exterior Lathing 4/10/2025 Partial Approval SCOTT SOBEL
PLUMBING-Rough 4/10/2025 Approved SCOTT SOBEL
BUILDING-Rough-Frame 4/11/2025 Approved ARUTYUN MADATYAN
Green Building Rough 4/11/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/11/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 4/28/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 9/4/2025 Approved ALEXANDER HANDY
Final 9/4/2025 OK to Issue CofO ALEXANDER HANDY
Footing/Foundation/Slab 9/4/2025 Approved ALEXANDER HANDY
Green Building Final 9/4/2025 Approved ALEXANDER HANDY
HVAC-Final 9/4/2025 Approved ALEXANDER HANDY
PLUMBING-Final 9/4/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 9/4/2025 Approved ALEXANDER HANDY