19544 W HAMLIN ST 91335
Certificate Information: 19544 W HAMLIN ST 91335
- Application / Permit
- 25014-20000-00063
- Plan Check / Job No.
- B25VN00315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENSLOSE (E) ATTACHED 14'-7" X 9'-5" PATIO COVER AND REMODEL TO (E) SFD. REMOVE FIRE PLACE AND WALL BETWEEN KITCHEN AND LIVING ROOM. INTERIOR REMODEL TO RELOCATE BEDROOM AND ADD 2 BATHROOMS.
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/14/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/17/2025 | APPLICANT |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 9/8/2025 | ALEXANDER HANDY |
| Permit Finaled | 10/2/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/2/2025 | MICHAEL PELHAM |
| CofO Issued | 10/2/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mobed,, Ashkan; Lic. No.: C92493 | 23450 KITTREDGE ST WEST HILLS, CA 91307 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/14/2025 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 2/24/2025 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 2/24/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 2/24/2025 | Partial Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/4/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 3/6/2025 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 3/6/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 3/6/2025 | Approved | ALEXANDER HANDY |
| Insulation | 3/11/2025 | Partial Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 3/11/2025 | Approved | ALEXANDER HANDY |
| Wood Frame | 3/11/2025 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 3/13/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Drywall Nailing | 3/17/2025 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 3/17/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Wood Construction | 4/7/2025 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 4/10/2025 | Approved | SCOTT SOBEL |
| HVAC-Rough | 4/10/2025 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | SCOTT SOBEL |
| PLUMBING-Rough | 4/10/2025 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/11/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 4/28/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| Final | 9/4/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 9/4/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/4/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 9/4/2025 | Approved | ALEXANDER HANDY |