7401 N COSTELLO AVE 91405
Certificate Information: 7401 N COSTELLO AVE 91405
- Application / Permit
- 25014-20000-00058
- Plan Check / Job No.
- B25VN00267
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO SFD LIVING SPACE. NEW REAR ADDITIONS TO THE (E) SINGLE FAMILY DWELLING. NEW ATTACHED TRELLIS. INTERIOR REMODEL TO THE SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2025 | JESSE ARELLANO |
| Corrections Issued | 1/15/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 1/17/2025 | APPLICANT |
| Plan Check Approved | 1/31/2025 | GIOVANNY CHAVEZ |
| Issued | 2/10/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/22/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Zumwalt Development Inc; Lic. No.: 1097342-B | 2980 ALLESANDRO ST APT 210 LOS ANGELES, CA 90039 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/11/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/18/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/18/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/26/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 3/26/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/26/2025 | Approved | VINCENT HANLEY |
| Wood Frame | 3/26/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/28/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/28/2025 | Partial Approval | VINCENT HANLEY |
| Insulation | 4/2/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/2/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/7/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/25/2025 | Approved | VINCENT HANLEY |
| Final | 7/25/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/25/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/25/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/25/2025 | Approved | VINCENT HANLEY |
| Final | 10/3/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 10/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 10/3/2025 | Approved | VINCENT HANLEY |