7401 N COSTELLO AVE 91405

Certificate Information: 7401 N COSTELLO AVE 91405

Application / Permit
25014-20000-00058
Plan Check / Job No.
B25VN00267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO SFD LIVING SPACE. NEW REAR ADDITIONS TO THE (E) SINGLE FAMILY DWELLING. NEW ATTACHED TRELLIS. INTERIOR REMODEL TO THE SINGLE FAMILY DWELLING.
Permit Issued
Issued on 2/10/2025
Issuing Office
West Los Angeles
Current Status
Issued on 2/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/14/2025 JESSE ARELLANO
Corrections Issued 1/15/2025 JESSE ARELLANO
Building Plans Picked Up 1/17/2025 APPLICANT
Plan Check Approved 1/31/2025 GIOVANNY CHAVEZ
Issued 2/10/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/22/2025 LEE GUILBEAUX
Sewer availability Cleared 1/22/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/22/2025 LEE GUILBEAUX

Contact Information

Contractor Zumwalt Development Inc; Lic. No.: 1097342-B 2980 ALLESANDRO ST APT 210      LOS ANGELES, CA 90039
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 2/11/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/11/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/18/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 2/18/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/26/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Corrections Issued VINCENT HANLEY
HVAC-Rough 3/26/2025 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 3/26/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/26/2025 Approved VINCENT HANLEY
Wood Frame 3/26/2025 Not Ready for Inspection VINCENT HANLEY
Deputy Wood Construction 3/28/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/28/2025 Approved VINCENT HANLEY
HVAC-Rough 3/28/2025 Partial Approval VINCENT HANLEY
Insulation 4/2/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/2/2025 Approved MICHEL ABAJAN
Drywall Nailing 4/7/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 7/25/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/25/2025 Approved VINCENT HANLEY
Final 7/25/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/25/2025 Approved VINCENT HANLEY
Green Building Rough 7/25/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/25/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/25/2025 Approved VINCENT HANLEY
Final 10/3/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 10/3/2025 Approved VINCENT HANLEY
PLUMBING-Final 10/3/2025 Approved VINCENT HANLEY