5972-5974 N JAMIESON AVE 91316

Certificate Information: 5972-5974 N JAMIESON AVE 91316

Application / Permit
25014-20000-00042
Plan Check / Job No.
B25VN00168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, CONVERSION OF (E) ATTACHED GARAGE TO BE PART OF SFD, AND ADDITIONS TO (E) SFD AND ADDITION OF JUNIOR ACCESSORY DWELLING UNIT ADDITIONS TO COMPLY WITH GC 66323(a)(1) AND 66333 PER ENGINEERING. NFPA-13D FIRE SPRINKLKER THRU-OUT
Permit Issued
Issued on 2/25/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2025 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 ALFRED RAMIREZ
Corrections Issued 1/12/2025 ALFRED RAMIREZ
Quality Review Completed 1/14/2025 STEVEN KIM
Building Plans Picked Up 1/15/2025 APPLICANT
Plan Check Approved 2/25/2025 ALFRED RAMIREZ
Issued 2/25/2025 APPLICANT
CofO in Progress 11/26/2025 MORRIS JACKSON
Permit Finaled 12/13/2025 MICHAEL PELHAM
CofO Issued 12/13/2025 MICHAEL PELHAM
Permit Finaled 12/13/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 1/22/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/22/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/23/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/23/2025 EDGAR ALCARAZ
ZI Cleared 1/30/2025 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2025 Partial Inspection MORRIS JACKSON
Deputy Drilled-In Anchors 5/6/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 5/7/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 5/20/2025 Partial Approval MORRIS JACKSON
Underground Mechanical 5/20/2025 Not Ready for Inspection MORRIS JACKSON
Wood Frame 5/20/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Approved JON MCHUGH
Wood Frame 6/16/2025 Corrections Issued JON MCHUGH
Deputy Steel/Welding 6/20/2025 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 7/2/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 7/2/2025 Approved MORRIS JACKSON
Green Building Rough 7/2/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 7/2/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 7/2/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 7/21/2025 Approved MORRIS JACKSON
Green Building Rough 7/21/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/21/2025 Partial Approval MORRIS JACKSON
Verify Sprinkler Sign Off 7/21/2025 Approved MORRIS JACKSON
Insulation 7/25/2025 Approved MORRIS JACKSON
Drywall Nailing 7/31/2025 Corrections Issued MORRIS JACKSON
Shower Pan 8/12/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/20/2025 Approved MORRIS JACKSON
Service/Power Release 10/7/2025 Not Ready for Inspection MORRIS JACKSON
Sewer 10/7/2025 Approved MORRIS JACKSON
Underground Mechanical 10/7/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 10/16/2025 Approved MORRIS JACKSON
Service/Power Release 10/16/2025 Approved MORRIS JACKSON
Drywall Nailing 11/25/2025 Approved MORRIS JACKSON
Final 11/25/2025 OK to Issue CofO MORRIS JACKSON
Green Building Final 11/25/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 11/25/2025 Approved MORRIS JACKSON