10413 N SCOVILLE AVE 91040

Certificate Information: 10413 N SCOVILLE AVE 91040

Application / Permit
25014-20000-00028
Plan Check / Job No.
B25VN00090
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT EXISTING GARAGE STORAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 4/18/2025
Issuing Office
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2025 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 ISIS ARGUETA
Corrections Issued 1/10/2025 ISIS ARGUETA
Applicant returned to address corrections 2/21/2025 ROSENDO MEDINA
Plan Check Approved 4/14/2025 ROSENDO MEDINA
Issued 4/18/2025 APPLICANT
CofO in Progress 4/21/2026 DAVID ANDERSON
Permit Finaled 5/15/2026 RUBEN SALAS
Permit Finaled 5/15/2026 RUBEN SALAS
CofO Issued 5/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/24/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/24/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/6/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 2/21/2025 ISIS ARGUETA
Specific Plan Cleared 3/12/2025 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 3/28/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 600 W MAIN ST STE 200      ALHAMBRA, CA 91801

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2025 Partial Inspection WILLIAM WREN
Sewer 7/29/2025 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 1/13/2026 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 1/15/2026 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Approved DAVID ANDERSON
Green Building Rough 1/15/2026 Not Ready for Inspection DAVID ANDERSON
Shower Pan 1/15/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/4/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 2/4/2026 Approved DAVID ANDERSON
Green Building Rough 2/4/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/4/2026 Partial Approval DAVID ANDERSON
PLUMBING-Rough 2/4/2026 Approved DAVID ANDERSON
Sewer 2/4/2026 Approved DAVID ANDERSON
Underground Mechanical 2/4/2026 Approved DAVID ANDERSON
Drywall Nailing 2/13/2026 Approved DAVID ANDERSON
Final 3/31/2026 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 3/31/2026 Approved DAVID ANDERSON
Green Building Final 3/31/2026 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/31/2026 Approved DAVID ANDERSON
Final 4/13/2026 OK to Issue CofO DAVID ANDERSON
Green Building Final 4/13/2026 Approved DAVID ANDERSON