5252 N BEEMAN AVE 91607
Certificate Information: 5252 N BEEMAN AVE 91607
- Application / Permit
- 25014-20000-00002
- Plan Check / Job No.
- B24VN27249
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition and remodel (E) 1-story SFD, demo (E) rear covered patio, enlarge master bathroom, add (N) bathroom and powder room
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- CofO Issued on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | MINA HABILI |
| Corrections Issued | 1/7/2025 | MINA HABILI |
| Applicant returned to address corrections | 1/29/2025 | MINA HABILI |
| Applicant returned to address corrections | 2/19/2025 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 2/26/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/2/2025 | ZAW HAN |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 12/16/2025 | WAYNE REGESTER |
| Permit Finaled | 3/19/2026 | RUBEN SALAS |
| CofO Issued | 3/19/2026 | RUBEN SALAS |
| Permit Finaled | 3/19/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2025 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 1/21/2025 | KEVIN CHUNG |
| Specific Plan | Cleared | 1/27/2025 | JOANNA MARROQUIN |
Contact Information
| Contractor | Bellagio Design Build Corporation; Lic. No.: 935571-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 3/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/18/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/20/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 3/20/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 3/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 3/28/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 4/10/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 4/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/15/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/21/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 6/10/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/10/2025 | Partial Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 6/10/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/17/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 8/7/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 8/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 8/7/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/19/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/19/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 8/25/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/25/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/16/2025 | Approved | WAYNE REGESTER |
| Final | 12/16/2025 | OK to Issue CofO | WAYNE REGESTER |
| PLUMBING-Final | 12/16/2025 | Approved | WAYNE REGESTER |