5252 N BEEMAN AVE 91607

Certificate Information: 5252 N BEEMAN AVE 91607

Application / Permit
25014-20000-00002
Plan Check / Job No.
B24VN27249
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Addition and remodel (E) 1-story SFD, demo (E) rear covered patio, enlarge master bathroom, add (N) bathroom and powder room
Permit Issued
Issued on 3/4/2025
Issuing Office
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/6/2025 MINA HABILI
Corrections Issued 1/7/2025 MINA HABILI
Applicant returned to address corrections 1/29/2025 MINA HABILI
Applicant returned to address corrections 2/19/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/26/2025 LAWRENCE QUIRANTE
Plan Check Approved 3/2/2025 ZAW HAN
Issued 3/4/2025 APPLICANT
CofO in Progress 12/16/2025 WAYNE REGESTER
Permit Finaled 3/19/2026 RUBEN SALAS
CofO Issued 3/19/2026 RUBEN SALAS
Permit Finaled 3/19/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2025 KEVIN CHUNG
Roof/Waste drainage to street Cleared 1/21/2025 KEVIN CHUNG
Specific Plan Cleared 1/27/2025 JOANNA MARROQUIN

Contact Information

Contractor Bellagio Design Build Corporation; Lic. No.: 935571-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/18/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 3/18/2025 Partial Approval GAREN HAYRAPETYAN
HVAC-Rough 3/18/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 3/18/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/20/2025 Partial Approval OGANES TARAKHCHYAN
Shower Pan 3/20/2025 Partial Approval OGANES TARAKHCHYAN
Insulation 3/24/2025 Partial Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/24/2025 Partial Approval GAREN HAYRAPETYAN
Drywall Nailing 3/28/2025 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 4/10/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 4/24/2025 Partial Approval GAREN HAYRAPETYAN
Sewer 4/24/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/15/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 5/21/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/2/2025 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/2/2025 Partial Approval OGANES TARAKHCHYAN
Insulation 6/10/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/10/2025 Partial Inspection GAREN HAYRAPETYAN
Shower Pan 6/10/2025 Approved MICHEL ABAJAN
Drywall Nailing 6/17/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/7/2025 Approved GAREN HAYRAPETYAN
Final 8/7/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 8/7/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 8/7/2025 Approved GAREN HAYRAPETYAN
Final 8/19/2025 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/19/2025 No Access for Inspection OGANES TARAKHCHYAN
Final 8/25/2025 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/25/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/16/2025 Approved WAYNE REGESTER
Final 12/16/2025 OK to Issue CofO WAYNE REGESTER
PLUMBING-Final 12/16/2025 Approved WAYNE REGESTER