16243 W COMMUNITY ST 91343
Certificate Information: 16243 W COMMUNITY ST 91343
- Application / Permit
- 25014-20000-00001
- Plan Check / Job No.
- B24VN27247
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- Current Status
- CofO Issued on 3/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 1/8/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 1/14/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/15/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/22/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/27/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/15/2025 | GIOVANNY CHAVEZ |
| Issued | 7/16/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 3/11/2026 | RUBEN SALAS |
| CofO Issued | 3/11/2026 | RUBEN SALAS |
| Permit Finaled | 3/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 7/13/2025 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/30/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 11/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/15/2025 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/15/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 12/15/2025 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 12/15/2025 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/18/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/18/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/24/2025 | Corrections Issued | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 1/5/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 1/5/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 1/5/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 1/9/2026 | Approved | MICHAEL CORTEZ |
| Final | 2/6/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 2/20/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |