16243 W COMMUNITY ST 91343

Certificate Information: 16243 W COMMUNITY ST 91343

Application / Permit
25014-20000-00001
Plan Check / Job No.
B24VN27247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 7/16/2025
Issuing Office
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/7/2025 ALEC MOUSAKHANIAN
Corrections Issued 1/8/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 1/14/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 1/15/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 1/22/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 1/27/2025 GIOVANNY CHAVEZ
Plan Check Approved 7/15/2025 GIOVANNY CHAVEZ
Issued 7/16/2025 APPLICANT
CofO in Progress 2/20/2026 GAREN HAYRAPETYAN
Permit Finaled 3/11/2026 RUBEN SALAS
CofO Issued 3/11/2026 RUBEN SALAS
Permit Finaled 3/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/11/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/11/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/13/2025 CARLOS AGUILERA
Private sewage disp. approval Cleared 7/13/2025 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 10/30/2025 Approved GAREN HAYRAPETYAN
Wood Frame 11/14/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Conditional Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/15/2025 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 12/15/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 12/15/2025 Corrections Issued DAVID ANDERSON
Wood Frame 12/15/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 12/18/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/18/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 12/18/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 12/18/2025 Approved GAREN HAYRAPETYAN
Insulation 12/24/2025 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 1/5/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 1/5/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 1/5/2026 Conditional Approval GAREN HAYRAPETYAN
Drywall Nailing 1/9/2026 Approved MICHAEL CORTEZ
Final 2/6/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/6/2026 Approved GAREN HAYRAPETYAN
Smoke Detectors 2/6/2026 Approved GAREN HAYRAPETYAN
Final 2/20/2026 OK to Issue CofO GAREN HAYRAPETYAN