809 W 62ND PL 90044

Certificate Information: 809 W 62ND PL 90044

Application / Permit
25014-10001-02174
Plan Check / Job No.
B25LA30602
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO (25014-20000-02174), TO REVISE SCOPE OF WORK TO "NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(2)."
Permit Issued
Issued on 8/28/2025
Issuing Office
Current Status
Issued on 8/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/28/2025 SAMUEL GONZALEZ
Corrections Issued 7/29/2025 SAMUEL GONZALEZ
Building Plans Picked Up 8/4/2025 APPLICANT
Applicant returned to address corrections 8/25/2025 NEHEMIAS RAMOS
Plan Check Approved 8/28/2025 SHANGQIN XIE
Issued 8/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/8/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 8/8/2025 MICHAEL BROWN
Sewer availability Cleared 8/8/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 8/15/2025 MICHAEL BROWN
Community Plan Implem. Overlay Cleared 8/21/2025 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/11/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 9/16/2025 Partial Approval BARRY HACHE
Sewer 9/16/2025 Approved BARRY HACHE
Footing/Foundation/Slab 9/23/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/17/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 11/17/2025 Partial Approval BARRY HACHE
ELECTRICAL-Rough 11/26/2025 Approved BARRY HACHE
HVAC-Rough 11/26/2025 Approved BARRY HACHE
PLUMBING-Rough 11/26/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 12/2/2025 Approved BARRY HACHE
Green Building Rough 12/2/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 12/2/2025 Approved BARRY HACHE
Insulation 12/9/2025 Approved ALEX COLIN
Special/Order Compliance 12/9/2025 Not Ready for Inspection ALEX COLIN
Drywall Nailing 12/11/2025 Approved BARRY HACHE
Interior/Exterior Lathing 12/11/2025 Approved BARRY HACHE
Shower Pan 12/17/2025 Approved ALEX COLIN
ELECTRICAL-Final 1/21/2026 Corrections Issued BARRY HACHE
Final 1/21/2026 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 1/21/2026 Approved BARRY HACHE
Smoke Detectors 1/21/2026 Approved BARRY HACHE
ELECTRICAL-Final 2/26/2026 Not Ready for Inspection BARRY HACHE
HVAC-Final 2/26/2026 Corrections Issued BARRY HACHE
PLUMBING-Final 2/26/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Final 3/24/2026 Corrections Issued BARRY HACHE