3443 S SEPULVEDA BLVD 90034
Certificate Information: 3443 S SEPULVEDA BLVD 90034
- Application / Permit
- 25014-10001-00633
- Plan Check / Job No.
- B25LA13786
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- Eplan SUPPLEMENTAL TO PERMIT # 25014-10000-00633 FOR INTERIOR T.I. TO (E) RETAIL/ GROCERY STORE ( no addition & no change of use).
- Permit Issued
- Issued on 1/30/2026
- Issuing Office
- Current Status
- Issued on 1/30/2026
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2025 | GARO TELMI |
| Corrections Issued | 4/22/2025 | GARO TELMI |
| Quality Review Completed | 4/30/2025 | DANIEL CHAN |
| Applicant returned to address corrections | 6/12/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/13/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/17/2025 | GARO TELMI |
| Assigned to Zoning Architect | 6/20/2025 | ERIC ROMERO |
| Applicant returned to address corrections | 7/2/2025 | GARO TELMI |
| Applicant returned to address corrections | 1/27/2026 | GARO TELMI |
| Plan Check Approved | 1/28/2026 | GARO TELMI |
| Issued | 1/30/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2025 | DIANA RENTERIA |
| Permit | Cleared | 4/24/2025 | DIANA RENTERIA |
| Low Impact Development (LID) | Cleared | 4/28/2025 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 5/5/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 5/12/2025 | LIAM ODONOVAN |
| Green Code | Cleared | 7/20/2025 | Daniel Chan |
| Driveway location | Cleared | 9/11/2025 | PEDRO AYALA |
| Internal circulation | Cleared | 9/11/2025 | PEDRO AYALA |
| Specific Plan | Cleared | 9/11/2025 | PEDRO AYALA |
| CPC | Cleared | 9/24/2025 | FIPE LEILUA |
| Comm Cor/Mini-Mall | Cleared | 9/24/2025 | FIPE LEILUA |
| Comm Cor/Mini-Mall | Cleared | 9/24/2025 | FIPE LEILUA |
| Miscellaneous | Cleared | 9/24/2025 | FIPE LEILUA |
| ZA Case | Cleared | 9/24/2025 | FIPE LEILUA |
| ZA Case | Cleared | 9/24/2025 | FIPE LEILUA |
| Miscellaneous | Cleared | 10/6/2025 | TREVOR QUAN |
| Food Service Establishment | Cleared | 12/18/2025 | ANSON PUA |
| DAS Clearance | Cleared | 1/15/2026 | Garo Telmi |
| Zoning Plan Check | Cleared | 1/22/2026 | ERIC ROMERO |
| Food establishment approval | Cleared | 1/27/2026 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 1/27/2026 | AL GAMBLE |
Contact Information
| Architect | Soares,, Christen F; Lic. No.: C32372 | 711 MARKET ST 2ND FLR SAN FRANCISCO, CA 94103 |
| Architect | Soares,, Christen F; Lic. No.: NA32372 | , |
| Contractor | Agi General Contracting; Lic. No.: 370609-B | 8210 KATELLA AVENUE SUITE I STANTON, CA 90680 |
| Contractor | Gautreau Art Inc; Lic. No.: 370609-B | 8210 KATELLA AVENUE SUITE I STANTON, CA 90680 |
| Engineer | Choi,, Michael; Lic. No.: C67851 | 1221 N ORANGE DR 217 LOS ANGELES, CA 90038 |
| Engineer | Treat,, Kevin; Lic. No.: S4947 | 3527 MOUNT DIABLO BLVD #242 LAFAYETTE, CA 94549 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 2/26/2026 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 3/5/2026 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 3/10/2026 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 3/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 3/20/2026 | Partial Approval | FARHAD DADBIN |
| Insulation | 3/26/2026 | Partial Approval | FARHAD DADBIN |
| Structural Steel Frame | 4/8/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 4/9/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/20/2026 | Partial Approval | FARHAD DADBIN |
| Insulation | 4/22/2026 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 4/22/2026 | Partial Approval | FARHAD DADBIN |
| T-Bar Ceiling | 6/12/2026 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 6/25/2026 | Approved | FARHAD DADBIN |