5649 W COLISEUM ST 90016
Certificate Information: 5649 W COLISEUM ST 90016
- Application / Permit
- 25014-10000-05795
- Plan Check / Job No.
- B25LA55131
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 1ST AND 2ND STORY ADDITIONS TO (E) ONE-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/17/2026
- Issuing Office
- Current Status
- Issued on 6/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/5/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 1/30/2026 | MEGAN KOLP |
| Corrections Issued | 2/18/2026 | HERNAN ARREOLA |
| Quality Review Completed | 2/24/2026 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 3/16/2026 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/14/2026 | HERNAN ARREOLA |
| Plan Check Approved | 5/27/2026 | HERNAN ARREOLA |
| Issued | 6/17/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/25/2026 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2026 | JEREMY CHOK |
| Sewer availability | Cleared | 3/27/2026 | JEREMY CHOK |
| GPI Written Notices | Cleared | 5/4/2026 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 5/4/2026 | HERNAN ARREOLA |
| Miscellaneous | Cleared | 5/15/2026 | CASEY JENSEN |
| Zoning Plan Check | Cleared | 5/21/2026 | MEGAN KOLP |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: NA83859 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/23/2026 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 6/25/2026 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 6/25/2026 | Approved | LUIS CASTRO |
| METHANE-Barrier | 6/25/2026 | Approved | LUIS CASTRO |
| METHANE-Subgrade | 6/25/2026 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 6/30/2026 | Partial Approval | LUIS CASTRO |
| Wood Frame | 6/30/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2026 | Partial Approval | LUIS CASTRO |
| Insulation | 7/6/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2026 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2026 | Partial Approval | ALIZAH MAYAGOITIA |