4312-4314 N NOBLE AVE 91403
Certificate Information: 4312-4314 N NOBLE AVE 91403
- Application / Permit
- 25014-10000-05586
- Plan Check / Job No.
- B25LA53346
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] 2nd story addition to (E) SFD and convert (E) garage into JADU
- Permit Issued
- Issued on 2/17/2026
- Issuing Office
- Current Status
- Issued on 2/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2025 | JOSEPH RAFOLS |
| Corrections Issued | 12/29/2025 | JOSEPH RAFOLS |
| Assigned to Zoning Architect | 1/2/2026 | HAYDON CHAN |
| Quality Review Completed | 1/5/2026 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/29/2026 | JOSEPH RAFOLS |
| Plan Check Approved | 2/17/2026 | JOSEPH RAFOLS |
| Issued | 2/17/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2026 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/22/2026 | CINDY QI |
| Grading Pre-Inspection | Cleared | 1/23/2026 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2026 | TONY CHIANG |
| Sewer availability | Cleared | 1/26/2026 | TONY CHIANG |
| Zoning Plan Check | Cleared | 2/12/2026 | HAYDON CHAN |
| GPI Written Notices | Cleared | 2/17/2026 | JOSEPH RAFOLS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Danialian,, Derik; Lic. No.: C94256 | 15904 INDEX ST. GRANADA HILLS, CA 91344 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2026 | Corrections Issued | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 3/12/2026 | Partial Approval | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 3/17/2026 | Corrections Issued | MICHAEL CORTEZ |
| Underground Mechanical | 3/17/2026 | Partial Approval | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2026 | Approved | WAYNE REGESTER |
| Wood Frame | 6/15/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 6/22/2026 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 6/24/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/29/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/29/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/1/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/1/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 7/1/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/6/2026 | Partial Approval | DAVID ANDERSON |
| Final | 7/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/6/2026 | Approved | DAVID ANDERSON |
| Green Building Final | 7/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 7/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 7/6/2026 | Partial Approval | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/6/2026 | Partial Approval | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/6/2026 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 7/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 7/6/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/9/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 7/9/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/9/2026 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2026 | Partial Inspection | MISAEL ESPARZA |
| Insulation | 7/14/2026 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/14/2026 | Partial Approval | MISAEL ESPARZA |
| Insulation | 7/15/2026 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/20/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 7/23/2026 | Approved | JAVIER RAMOS JR |