1844 W 39TH ST 90062

Certificate Information: 1844 W 39TH ST 90062

Application / Permit
25014-10000-05580
Plan Check / Job No.
B25LA53317
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION TO REAR OF (E) SFD, INTERIOR REMODEL TO (E) SFD INCLUDING, KITCHEN LAYOUT CHANGE, REPLACING DRYWALL, REMODELING BATHROOMS, AND REMOVING/REPLACING WINDOWS, ALL WORK PER ENG.
Permit Issued
Issued on 1/20/2026
Issuing Office
Current Status
Issued on 1/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2025 APPLICANT
Assigned to Plan Check Engineer 12/26/2025 LUISANGEL VALENZUELA
Corrections Issued 12/27/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 1/9/2026 ALEC MOUSAKHANIAN
Plan Check Approved 1/16/2026 OMAR GARNICA
Issued 1/20/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/12/2026 STEVE MELGAR
Roof/Waste drainage to street Cleared 1/12/2026 STEVE MELGAR
Sewer availability Cleared 1/12/2026 STEVE MELGAR

Contact Information

Contractor Periel Construction Inc; Lic. No.: 1138571-B       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/23/2026 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/23/2026 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/28/2026 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 1/28/2026 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 1/28/2026 Approved SABAS ALONSO
Green Building Rough 1/28/2026 Partial Approval SABAS ALONSO
HVAC-Rough 1/28/2026 Partial Approval SABAS ALONSO
PLUMBING-Rough 1/28/2026 Partial Approval SABAS ALONSO
Insulation 1/30/2026 Partial Approval SABAS ALONSO
Drywall Nailing 2/4/2026 Partial Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Partial Approval ALEX COLIN
BUILDING-Rough-Frame 3/13/2026 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/13/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 3/13/2026 Partial Approval SABAS ALONSO
PLUMBING-Rough 3/13/2026 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/6/2026 Approved SABAS ALONSO
ELECTRICAL-Rough 4/6/2026 Approved SABAS ALONSO
HVAC-Rough 4/6/2026 Approved SABAS ALONSO
PLUMBING-Rough 4/6/2026 Approved SABAS ALONSO
Insulation 4/8/2026 Approved SABAS ALONSO
Drywall Nailing 4/14/2026 Approved SABAS ALONSO
Shower Pan 4/14/2026 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 4/21/2026 Partial Approval ALEX COLIN