18023 W TIARA ST 91316
Certificate Information: 18023 W TIARA ST 91316
- Application / Permit
- 25014-10000-05365
- Plan Check / Job No.
- B25LA51315
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Addition and remodel to (E) single family dwelling. Enlarge (E) attached garage. NFPA 13D all throughout.
- Permit Issued
- Issued on 1/29/2026
- Issuing Office
- Current Status
- Issued on 1/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2025 | ALEXANDER JOO |
| Assigned to Zoning Architect | 12/11/2025 | LY CHEA |
| Corrections Issued | 12/13/2025 | ALEXANDER JOO |
| Quality Review Completed | 12/16/2025 | GARO TELMI |
| Applicant returned to address corrections | 1/8/2026 | ALEXANDER JOO |
| Applicant returned to address corrections | 1/20/2026 | ALEXANDER JOO |
| Plan Check Approved | 1/29/2026 | ALEXANDER JOO |
| Issued | 1/29/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/16/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 12/18/2025 | MICHAEL BROWN |
| Supp. Use District POD/CDO/TDO | Cleared | 1/20/2026 | GEORGIA SMITH |
| Zoning Plan Check | Cleared | 1/23/2026 | LY CHEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: NA73151 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/26/2026 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 3/2/2026 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 3/17/2026 | Partial Approval | MORRIS JACKSON |
| Insulation | 3/19/2026 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | JON MCHUGH |
| Green Building Rough | 5/19/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 5/19/2026 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 5/19/2026 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/19/2026 | Approved | JON MCHUGH |
| Insulation | 5/22/2026 | Partial Approval | JON MCHUGH |
| Shower Pan | 5/22/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 5/28/2026 | Approved | JON MCHUGH |
| Drywall Nailing | 6/4/2026 | Approved | JON MCHUGH |
| Gas Test | 6/8/2026 | Approved | HENRY KIM |