2426 N RICHELIEU AVE 90032

Certificate Information: 2426 N RICHELIEU AVE 90032

Application / Permit
25014-10000-05359
Plan Check / Job No.
B25LA51284
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW REAR ADDITION TO EXISTING SINGLE FAMILY DWELLING FOR BEDROOM, NEW BATHROOM AND CLOSET.
Permit Issued
Issued on 12/31/2025
Issuing Office
Metro
Current Status
CofO Issued on 6/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2025 APPLICANT
Assigned to Plan Check Engineer 12/10/2025 ADAM HEGAZI
Corrections Issued 12/11/2025 ADAM HEGAZI
Building Plans Picked Up 12/18/2025 APPLICANT
Applicant returned to address corrections 12/24/2025 ADAM HEGAZI
Plan Check Approved 12/29/2025 CRISTINA SALAZAR
Issued 12/31/2025 APPLICANT
CofO in Progress 6/12/2026 LILIANA PORTILLO
Permit Finaled 6/15/2026 DEROLD HAUFF
CofO Issued 6/15/2026 DEROLD HAUFF
Permit Finaled 6/15/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/24/2025 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 12/26/2025 ROSE STEIN-WENDT
Grading Pre-Inspection Cleared 12/29/2025 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/11/2026 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/13/2026 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/13/2026 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 4/28/2026 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 5/5/2026 Corrections Issued LILIANA PORTILLO
HVAC-Rough 5/5/2026 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 5/5/2026 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/7/2026 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/7/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 5/7/2026 Approved ALIZAH MAYAGOITIA
Insulation 5/12/2026 Corrections Issued GEM DE OCAMPO
Drywall Nailing 5/14/2026 Approved GEM DE OCAMPO
Insulation 5/14/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 5/14/2026 Approved GEM DE OCAMPO
Final 5/22/2026 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/22/2026 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/22/2026 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 5/22/2026 Not Ready for Inspection OSVALDO PARAMO
Final 6/4/2026 Corrections Issued OSVALDO PARAMO
Green Building Final 6/4/2026 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/4/2026 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 6/4/2026 Approved OSVALDO PARAMO
ELECTRICAL-Final 6/11/2026 Approved LILIANA PORTILLO
Final 6/11/2026 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 6/11/2026 Approved LILIANA PORTILLO
PLUMBING-Final 6/11/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/11/2026 SGSOV Approved LILIANA PORTILLO