2426 N RICHELIEU AVE 90032
Certificate Information: 2426 N RICHELIEU AVE 90032
- Application / Permit
- 25014-10000-05359
- Plan Check / Job No.
- B25LA51284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW REAR ADDITION TO EXISTING SINGLE FAMILY DWELLING FOR BEDROOM, NEW BATHROOM AND CLOSET.
- Permit Issued
- Issued on 12/31/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2025 | ADAM HEGAZI |
| Corrections Issued | 12/11/2025 | ADAM HEGAZI |
| Building Plans Picked Up | 12/18/2025 | APPLICANT |
| Applicant returned to address corrections | 12/24/2025 | ADAM HEGAZI |
| Plan Check Approved | 12/29/2025 | CRISTINA SALAZAR |
| Issued | 12/31/2025 | APPLICANT |
| CofO in Progress | 6/12/2026 | LILIANA PORTILLO |
| Permit Finaled | 6/15/2026 | DEROLD HAUFF |
| CofO Issued | 6/15/2026 | DEROLD HAUFF |
| Permit Finaled | 6/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/24/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2025 | ROSE STEIN-WENDT |
| Grading Pre-Inspection | Cleared | 12/29/2025 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/13/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/13/2026 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/28/2026 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/5/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 5/5/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/5/2026 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/7/2026 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 5/7/2026 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/12/2026 | Corrections Issued | GEM DE OCAMPO |
| Drywall Nailing | 5/14/2026 | Approved | GEM DE OCAMPO |
| Insulation | 5/14/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 5/14/2026 | Approved | GEM DE OCAMPO |
| Final | 5/22/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/22/2026 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/22/2026 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 5/22/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 6/4/2026 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/4/2026 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 6/4/2026 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/11/2026 | Approved | LILIANA PORTILLO |
| Final | 6/11/2026 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 6/11/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 6/11/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/11/2026 | SGSOV Approved | LILIANA PORTILLO |