1657 W 256TH ST 90710
Certificate Information: 1657 W 256TH ST 90710
- Application / Permit
- 25014-10000-05325
- Plan Check / Job No.
- B25LA50798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Ground floor and (N) porch addition to (E) 1-story SFD
- Permit Issued
- Issued on 2/10/2026
- Issuing Office
- Current Status
- Issued on 2/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2025 | DAVID CASTILLO |
| Corrections Issued | 12/8/2025 | DAVID CASTILLO |
| Plan Check Approved | 1/29/2026 | DAVID CASTILLO |
| Issued | 2/10/2026 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/11/2025 | DANIEL CORONADO |
| Address approval | Cleared | 1/8/2026 | TONY CHIANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2026 | TONY CHIANG |
| Sewer availability | Cleared | 1/8/2026 | TONY CHIANG |
| Roof/Waste drainage to street | Cleared | 1/12/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2026 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 3/12/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 3/12/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/17/2026 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 3/17/2026 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/17/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/23/2026 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 3/23/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 3/23/2026 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Partial Approval | EUGENE CASSIDY |
| Insulation | 3/24/2026 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/23/2026 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 4/23/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/13/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 5/13/2026 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/21/2026 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 5/21/2026 | Approved | EUGENE CASSIDY |
| Wood Frame | 5/21/2026 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/3/2026 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 6/3/2026 | Partial Approval | EUGENE CASSIDY |