1748 N STANLEY AVE 90046

Certificate Information: 1748 N STANLEY AVE 90046

Application / Permit
25014-10000-05298
Plan Check / Job No.
B25LA50532
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert (e) garage into new adu, including addition PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k) NFPA-13D
Permit Issued
Issued on 3/10/2026
Issuing Office
Current Status
Issued on 3/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/2/2025 APPLICANT
Assigned to Plan Check Engineer 12/5/2025 CRYSTEL MAALOUF
Corrections Issued 12/8/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 1/7/2026 RICARDO RAMIREZ
Applicant returned to address corrections 2/6/2026 NGHI SU
Applicant returned to address corrections 2/11/2026 NGHI SU
Applicant returned to address corrections 2/20/2026 LAWRENCE QUIRANTE
Plan Check Approved 3/3/2026 EDWIN MARTINEZ
Issued 3/10/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/29/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 1/5/2026 JESUS CISNEROS
Sewer availability Cleared 1/5/2026 JESUS CISNEROS
Grading Pre-Inspection Cleared 1/8/2026 JONATHAN HOM
Roof/Waste drainage to street Cleared 1/12/2026 JESUS CISNEROS
Street Frontage Cleared 1/12/2026 JESUS CISNEROS
Hydrant and Access approval Cleared 2/18/2026 PATRICK PEREZ

Contact Information

Architect Perella,, Ryan Adam; Lic. No.: NA30833       ,
Contractor Future Builders & Design Inc; Lic. No.: 1058468-B       ,
Engineer Sayah,, Daniel H; Lic. No.: NA67905       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/13/2026 Approved ROY SPAULDING
Underground Mechanical 3/13/2026 Partial Approval ROY SPAULDING
Deputy Drilled-In Anchors 3/18/2026 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 3/19/2026 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 4/15/2026 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Partial Approval ROY SPAULDING
HVAC-Rough 4/15/2026 Approved ROY SPAULDING
PLUMBING-Rough 4/15/2026 Approved ROY SPAULDING
Deputy Wood Construction 4/20/2026 Conditional Approval ROY SPAULDING
BUILDING-Rough-Frame 4/22/2026 Approved ROY SPAULDING
Green Building Rough 4/22/2026 Approved ROY SPAULDING
Wood Frame 4/22/2026 Approved ROY SPAULDING
Interior/Exterior Lathing 4/30/2026 Approved ROY SPAULDING
Insulation 5/12/2026 Approved ROY SPAULDING
Drywall Nailing 5/15/2026 Approved ROY SPAULDING