209 N QUADRO VECCHIO DR 90272
Certificate Information: 209 N QUADRO VECCHIO DR 90272
- Application / Permit
- 25014-10000-05123
- Plan Check / Job No.
- B25LA48764
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2025 WILDFIRE REBUILD, DETACHED GARAGE AND NEW ACCESSORY DWELLING UNIT AT SECOND FLOOR & ATTACHED DECK PER LAMC 12.22 A.33(c)(4)., TWO-STORY, 35' X 20'. EO1.
- Permit Issued
- Issued on 4/23/2026
- Issuing Office
- Current Status
- Issued on 4/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2026 | SERGIO GUTIERREZ |
| Corrections Issued | 1/20/2026 | SERGIO GUTIERREZ |
| Quality Review Completed | 1/26/2026 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 3/17/2026 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/8/2026 | SERGIO GUTIERREZ |
| Issued | 4/23/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2026 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 1/21/2026 | DAVID VO |
| Sewer availability | Cleared | 1/21/2026 | DAVID VO |
| Address approval | Cleared | 1/27/2026 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 2/13/2026 | KURT CORRAL |
| Miscellaneous | Cleared | 2/19/2026 | KENTON TRINH |
Contact Information
| Contractor | J B General Contractors; Lic. No.: 441135-B | 1160 SOUTH SWALL DRIVE LOS ANGELES, CA 90035 |
| Engineer | Funk,, David Lyle; Lic. No.: NA5421 | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2026 | Corrections Issued | MICHAEL ALLEN |
| Reinforced Concrete Frame | 5/18/2026 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 5/20/2026 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/3/2026 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/4/2026 | No Result Entered | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/5/2026 | No Result Entered | JUAN VALENZUELA |