4521 1/4 W FINLEY AVE 90027

Certificate Information: 4521 1/4 W FINLEY AVE 90027

Application / Permit
25014-10000-05022
Plan Check / Job No.
B25LA14374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
2-story addition to a detached garage for an ADU per state law SB 1211.
Permit Issued
Issued on 1/20/2026
Issuing Office
Current Status
Issued on 1/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 HELEN NGUYEN
Assigned to Zoning Architect 4/17/2025 ELAHE MERRIKHI
Corrections Issued 4/22/2025 HELEN NGUYEN
Quality Review Completed 4/24/2025 PETER KIM
Applicant returned to address corrections 6/6/2025 HELEN NGUYEN
Applicant returned to address corrections 10/30/2025 HELEN NGUYEN
Applicant returned to address corrections 12/30/2025 HELEN NGUYEN
Plan Check Approved 1/16/2026 HELEN NGUYEN
Issued 1/20/2026 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 11/20/2025 MARCO SANCHEZ
Address approval Cleared 11/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/21/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 11/21/2025 MICHAEL BROWN
Sewer availability Cleared 11/21/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 11/24/2025 LAVEON RIDER
Highway dedication Cleared 11/26/2025 CINDY QI
GPI Written Notices Cleared 12/17/2025 HELEN NGUYEN
Grading Pre-Inspection Cleared 12/17/2025 HELEN NGUYEN
Zoning Plan Check Cleared 1/16/2026 ELAHE MERRIKHI

Contact Information

Contractor Hta Construction & Development; Lic. No.: 1044038-B 3639 ATLANTIC AVE      LONG BEACH, CA 90807
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2026 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/10/2026 Approved ENRIQUE MIRELES
Sewer 3/3/2026 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 3/5/2026 Conditional Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 3/12/2026 Approved ENRIQUE MIRELES
Wood Frame 3/27/2026 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Corrections Issued ENRIQUE MIRELES
Wood Frame 4/27/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/8/2026 Corrections Issued ENRIQUE MIRELES
HVAC-Rough 5/8/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/8/2026 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/21/2026 Approved ENRIQUE MIRELES
HVAC-Rough 5/21/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/21/2026 Approved ENRIQUE MIRELES
Wood Frame 5/21/2026 Approved ENRIQUE MIRELES
Shower Pan 5/29/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/9/2026 Approved ENRIQUE MIRELES
Wood Frame 6/9/2026 Approved ENRIQUE MIRELES
Insulation 6/15/2026 Approved ENRIQUE MIRELES
Drywall Nailing 6/24/2026 Approved ENRIQUE MIRELES
Green Building Rough 6/24/2026 Approved ENRIQUE MIRELES
Sewer 6/24/2026 Approved ENRIQUE MIRELES