2125 S WALGROVE AVE 90066
Certificate Information: 2125 S WALGROVE AVE 90066
- Application / Permit
- 25014-10000-04968
- Plan Check / Job No.
- B25LA47207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION TO (E) SFD 130 SQ. FT.
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 11/15/2025 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 11/18/2025 | APPLICANT |
| Plan Check Approved | 12/2/2025 | SUNMIN LEE |
| Issued | 12/2/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | RUBEN RIVAS |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
| CofO Issued | 6/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 11/26/2025 | BIAINA HARITUNIAN |
| Specific Plan | Cleared | 12/2/2025 | RICHARD WOO |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2026 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/27/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 2/6/2026 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 2/6/2026 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | RUBEN RIVAS |
| Insulation | 2/12/2026 | Approved | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 3/17/2026 | Approved | MICHAEL ALLEN |
| Insulation | 3/23/2026 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/23/2026 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 3/23/2026 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/25/2026 | Partial Approval | RUBEN RIVAS |
| Insulation | 3/25/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 3/31/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/31/2026 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 5/5/2026 | Approved | RUBEN RIVAS |
| Final | 5/5/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 5/5/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 5/5/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 5/5/2026 | Approved | RUBEN RIVAS |
| Final | 5/12/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 5/12/2026 | Corrections Issued | RUBEN RIVAS |
| Final | 5/19/2026 | OK to Issue CofO | RUBEN RIVAS |
| Green Building Final | 5/19/2026 | Approved | RUBEN RIVAS |