3651 1/2 S ARLINGTON AVE 90018
Certificate Information: 3651 1/2 S ARLINGTON AVE 90018
- Application / Permit
- 25014-10000-04927
- Plan Check / Job No.
- B25LA46584
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERTING OF EXISTING GARAGE AND ADDITION TO STATE ACCESSORY DWELLING UINT PER GC 66323(a)(2). REMOVE PORTION OF EXISTING GARAGE.
- Permit Issued
- Issued on 5/27/2026
- Issuing Office
- Current Status
- Issued on 5/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2025 | PINANK PATEL |
| Corrections Issued | 11/8/2025 | PINANK PATEL |
| Applicant returned to address corrections | 1/9/2026 | PINANK PATEL |
| Applicant returned to address corrections | 1/20/2026 | PINANK PATEL |
| Plan Check Approved | 4/10/2026 | PINANK PATEL |
| Plan Check Approved | 5/10/2026 | PINANK PATEL |
| No Progress | 5/26/2026 | PINANK PATEL |
| Issued | 5/27/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2025 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2025 | JEANIE LAM |
| Sewer availability | Cleared | 12/15/2025 | JEANIE LAM |
| Address approval | Cleared | 12/19/2025 | JEANIE LAM |
| City Hist. Cultural Monument | Cleared | 4/7/2026 | DANIEL MATA |
| Historic monument | Cleared | 4/7/2026 | DANIEL MATA |
| ZI | Cleared | 4/7/2026 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Shower Pan | 8/6/2026 Time Frame: 12-2 |
Inspection Request History
| Sewer | 5/29/2026 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 5/29/2026 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 5/29/2026 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 6/12/2026 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 6/12/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 7/15/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/16/2026 | Approved Pending GreenApproval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 7/16/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/20/2026 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 7/23/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 7/23/2026 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 8/4/2026 | Approved | JUSTIN HAWLEY |