6203 N YARMOUTH AVE 91316

Certificate Information: 6203 N YARMOUTH AVE 91316

Application / Permit
25014-10000-04909
Plan Check / Job No.
B25LA46345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33.
Permit Issued
Issued on 1/22/2026
Issuing Office
Current Status
Issued on 1/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/5/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 ROSENDO MEDINA
Corrections Issued 11/8/2025 ROSENDO MEDINA
Applicant returned to address corrections 11/27/2025 ROSENDO MEDINA
Applicant returned to address corrections 1/9/2026 ARAMIK SHAHMIRZAIAN
Plan Check Approved 1/15/2026 ROSENDO MEDINA
Issued 1/22/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/20/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 11/20/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 11/26/2025 JESUS CISNEROS
Sewer availability Cleared 11/26/2025 JESUS CISNEROS
Construction near power lines Cleared 1/7/2026 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 7/27/2026   
Floor/Roof Diaphrgm/Shear Wall 7/27/2026   
Insulation 7/27/2026   
PLUMBING-Rough 7/27/2026   

Inspection Request History

PLUMBING-Rough 5/14/2026 Partial Approval JON MCHUGH
Deputy Drilled-In Anchors 5/20/2026 Conditional Approval JON MCHUGH
Footing/Foundation/Slab 5/22/2026 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 6/25/2026 Not Ready for Inspection JON MCHUGH
HVAC-Rough 6/25/2026 Corrections Issued JON MCHUGH
PLUMBING-Rough 6/25/2026 Not Ready for Inspection JON MCHUGH
Gas Test 7/2/2026 Corrections Issued JEFFREY HARTLINE
HVAC-Rough 7/2/2026 Approved JEFFREY HARTLINE
PLUMBING-Rough 7/2/2026 Approved JEFFREY HARTLINE
Sewer 7/2/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 7/15/2026 Partial Approval IVAN SARABIA
Gas Test 7/15/2026 Corrections Issued IVAN SARABIA
Interior/Exterior Lathing 7/15/2026 Corrections Issued IVAN SARABIA
Special/Order Compliance 7/15/2026 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 7/22/2026 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 7/22/2026 Partial Approval JON MCHUGH
PLUMBING-Rough 7/22/2026 Not Ready for Inspection JON MCHUGH
Deputy Drilled-In Anchors 7/23/2026 Conditional Approval JON MCHUGH