6009 E ROY ST 90042
Certificate Information: 6009 E ROY ST 90042
- Application / Permit
- 25014-10000-04832
- Plan Check / Job No.
- B25LA45768
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN 2nd story addition of Accessory Dwelling Unit per GCS 66323(a)(2) over (E) detached garage. NFPA 13D all throughout.
- Permit Issued
- Issued on 3/2/2026
- Issuing Office
- Current Status
- Issued on 3/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2025 | ALEXANDER JOO |
| Assigned to Zoning Architect | 11/13/2025 | SARHAD GHEVANDIAN |
| Corrections Issued | 11/17/2025 | ALEXANDER JOO |
| Quality Review Completed | 11/20/2025 | ARMEN JIVALAGIAN |
| Plan Check Approved | 3/2/2026 | ALEXANDER JOO |
| Issued | 3/2/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2025 | JESUS CISNEROS |
| Hydrant and Access approval | Cleared | 12/18/2025 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 1/6/2026 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 1/13/2026 | JESUS CISNEROS |
| Zoning Plan Check | Cleared | 2/17/2026 | SARHAD GHEVANDIAN |
| Grading Pre-Inspection | Cleared | 3/2/2026 | RAMAZANALI ALMASI |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| Interior/Exterior Lathing | 6/9/2026 |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 3/31/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Corrections Issued | DAVID WILLIAMS |
| Green Building Rough | 3/31/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 3/31/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Wood Frame | 3/31/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/7/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/7/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/9/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Deputy Drilled-In Anchors | 4/9/2026 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/9/2026 | Corrections Issued | RONNIE MEDINA |
| Green Building Rough | 4/9/2026 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Rough | 4/9/2026 | Approved | RONNIE MEDINA |
| Sewer | 4/9/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Underground Mechanical | 4/9/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Wood Frame | 4/9/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Footing/Foundation/Slab | 4/14/2026 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 4/29/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 4/29/2026 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 4/29/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Wood Frame | 4/29/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Partial Approval | DAVID WILLIAMS |
| HVAC-Rough | 5/5/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/5/2026 | Approved | DAVID WILLIAMS |
| Sewer | 5/5/2026 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 5/5/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/21/2026 | Approved | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 5/26/2026 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/1/2026 | Corrections Issued | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 6/1/2026 | Corrections Issued | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/1/2026 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/3/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/3/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 6/5/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 6/5/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Shower Pan | 6/5/2026 | Approved | GEM DE OCAMPO |