2616 1/2 E DOBINSON ST 90033
Certificate Information: 2616 1/2 E DOBINSON ST 90033
- Application / Permit
- 25014-10000-04824
- Plan Check / Job No.
- B25LA45675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 2-CAR GARAGE TO ADU WITH NEW ADDITION PER WFPP.
- Permit Issued
- Issued on 2/3/2026
- Issuing Office
- Metro
- Current Status
- Issued on 2/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2025 | ADAM HEGAZI |
| Corrections Issued | 11/5/2025 | ADAM HEGAZI |
| Building Plans Picked Up | 11/14/2025 | APPLICANT |
| Plan Check Approved | 1/23/2026 | ADAM HEGAZI |
| Issued | 2/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2025 | XOCHITL ARQUIETA |
| Tenant Habitability Plan | Cleared | 1/16/2026 | ARIC DEFUSCO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2026 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 1/20/2026 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 1/20/2026 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2026 | Partial Approval | JOSH MEISTER |
| PLUMBING-Rough | 3/24/2026 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2026 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 5/6/2026 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/6/2026 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Partial Approval | DAVID WILLIAMS |
| Green Building Rough | 5/6/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 5/6/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/6/2026 | Approved | DAVID WILLIAMS |
| Insulation | 5/15/2026 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/15/2026 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 5/21/2026 | Approved | OSVALDO PARAMO |