1411 N CORONADO ST 90026
Certificate Information: 1411 N CORONADO ST 90026
- Application / Permit
- 25014-10000-04771
- Plan Check / Job No.
- B25LA45105
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 2/19/2026
- Issuing Office
- Metro
- Current Status
- Issued on 2/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | KHEDER ALRAZAA |
| Assigned to Zoning Architect | 10/30/2025 | KAREN MEZA-MORALES |
| Corrections Issued | 11/1/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 11/7/2025 | KEN GILL |
| Building Plans Picked Up | 11/14/2025 | APPLICANT |
| Plan Check Approved | 2/13/2026 | KHEDER ALRAZAA |
| Issued | 2/19/2026 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/13/2025 | JOHN CONNEALLY |
| Sewer availability | Cleared | 11/25/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 12/18/2025 | TONY CHIANG |
| Zoning Plan Check | Cleared | 2/3/2026 | KAREN MEZA-MORALES |
| Grading Pre-Inspection | Cleared | 2/13/2026 | KHEDER ALRAZAA |
Contact Information
| Contractor | Capriwell Development And Construction; Lic. No.: 1077424-B | 301 N LAKE AVE, SUITE 600 PASADENA, CA 91101 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/31/2026 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/31/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/23/2026 | Approved | HAMIK HARTOUNIAN |