3817 S SOMERSET DR 90008

Certificate Information: 3817 S SOMERSET DR 90008

Application / Permit
25014-10000-04704
Plan Check / Job No.
B25LA44471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: NEW ADDITION TO (E) SINGLE FAMILY DWELLING UNIT. ALL WORK PER WFPP
Permit Issued
Issued on 1/15/2026
Issuing Office
Current Status
Issued on 1/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/23/2025 APPLICANT
Assigned to Plan Check Engineer 10/27/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 10/28/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 12/4/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 1/6/2026 ARAMIK SHAHMIRZAIAN
Plan Check Approved 1/13/2026 ARAMIK SHAHMIRZAIAN
Issued 1/15/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/3/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/3/2025 CARLOS AGUILERA
Sewer availability Cleared 11/3/2025 CARLOS AGUILERA
CPC Cleared 11/5/2025 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2026 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 2/5/2026 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 2/11/2026 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 2/19/2026 Conditional Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 2/26/2026 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Partial Approval LUIS CASTRO
PLUMBING-Rough 3/12/2026 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/18/2026 Partial Approval LUIS CASTRO
Insulation 3/18/2026 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 4/2/2026 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 4/2/2026 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Approved LUIS CASTRO
HVAC-Rough 4/2/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 4/10/2026 Partial Approval ALEX COLIN
Shower Pan 4/10/2026 Approved ALEX COLIN
BUILDING-Rough-Frame 4/14/2026 Approved LUIS CASTRO
Green Building Rough 4/14/2026 Approved LUIS CASTRO
Insulation 4/14/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 4/14/2026 Partial Approval LUIS CASTRO
Drywall Nailing 4/15/2026 Approved ALEX COLIN
Interior/Exterior Lathing 4/15/2026 Approved ALEX COLIN
ELECTRICAL-Final 7/6/2026 Approved LUIS CASTRO
Final 7/6/2026 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 7/6/2026 Approved LUIS CASTRO
Green Building Final 7/6/2026 Approved LUIS CASTRO
HVAC-Final 7/6/2026 Approved LUIS CASTRO
PLUMBING-Final 7/6/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 7/6/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 7/6/2026 Approved LUIS CASTRO