813 E COLDEN AVE 90002
Certificate Information: 813 E COLDEN AVE 90002
- Application / Permit
- 25014-10000-04648
- Plan Check / Job No.
- B25LA43773
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Addition to and conversion of (e) detached garage to an ADU (537sf) per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 1/2/2026
- Issuing Office
- Current Status
- Issued on 1/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2025 | JOHN MESIAS |
| Corrections Issued | 10/23/2025 | JOHN MESIAS |
| Plan Check Approved | 12/30/2025 | REZA HAGHIGHAT |
| Issued | 1/2/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 11/25/2025 | ABEL CASILLAS |
| Construction near power lines | Cleared | 12/26/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/29/2025 | ABEL CASILLAS |
Contact Information
| Contractor | Sire Energy Inc; Lic. No.: 1027415-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/13/2026 | Partial Inspection | ARTHUR NEGRETE |
| Underground Mechanical | 1/13/2026 | Approved | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 1/16/2026 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 1/16/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/30/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 1/30/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 2/2/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 2/9/2026 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/9/2026 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 2/9/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/9/2026 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/9/2026 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/9/2026 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 2/9/2026 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 2/19/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 2/27/2026 | Approved | ARTHUR NEGRETE |
| Sewer | 2/27/2026 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 2/27/2026 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 3/26/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/13/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/13/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 4/13/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/13/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/13/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/13/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/13/2026 | Approved | ARTHUR NEGRETE |