813 E COLDEN AVE 90002

Certificate Information: 813 E COLDEN AVE 90002

Application / Permit
25014-10000-04648
Plan Check / Job No.
B25LA43773
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Addition to and conversion of (e) detached garage to an ADU (537sf) per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 1/2/2026
Issuing Office
Current Status
Issued on 1/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/18/2025 APPLICANT
Assigned to Plan Check Engineer 10/22/2025 JOHN MESIAS
Corrections Issued 10/23/2025 JOHN MESIAS
Plan Check Approved 12/30/2025 REZA HAGHIGHAT
Issued 1/2/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/25/2025 ABEL CASILLAS
Roof/Waste drainage to street Cleared 11/25/2025 ABEL CASILLAS
Construction near power lines Cleared 12/26/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/29/2025 ABEL CASILLAS
Sewer availability Cleared 12/29/2025 ABEL CASILLAS

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/13/2026 Partial Inspection ARTHUR NEGRETE
Underground Mechanical 1/13/2026 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 1/16/2026 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 1/16/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 1/30/2026 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 1/30/2026 Not Ready for Inspection BEN MOLSTAD
Pre-Inspection 2/2/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 2/9/2026 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/9/2026 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Partial Approval JOSEPH MCGARRY
Green Building Rough 2/9/2026 Approved JOSEPH MCGARRY
HVAC-Rough 2/9/2026 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 2/9/2026 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 2/9/2026 Approved JOSEPH MCGARRY
Underground Mechanical 2/9/2026 Partial Approval JOSEPH MCGARRY
Insulation 2/19/2026 Approved ARTHUR NEGRETE
Drywall Nailing 2/27/2026 Approved ARTHUR NEGRETE
Sewer 2/27/2026 Approved ARTHUR NEGRETE
Underground Mechanical 2/27/2026 Approved ARTHUR NEGRETE
Underground Mechanical 3/26/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/13/2026 Approved ARTHUR NEGRETE
Final 4/13/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 4/13/2026 Approved ARTHUR NEGRETE
HVAC-Final 4/13/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 4/13/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 4/13/2026 Approved ARTHUR NEGRETE