3319-3321 S KEESHEN DR 90066
Certificate Information: 3319-3321 S KEESHEN DR 90066
- Application / Permit
- 25014-10000-04629
- Plan Check / Job No.
- B25LA43523
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ADDITION AND REMODEL OF 2 STORY SFD + NEW ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 1/16/2026
- Issuing Office
- Current Status
- Issued on 1/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 10/21/2025 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 10/23/2025 | KAITA SAITO |
| Quality Review Completed | 10/28/2025 | PRANITA SHAH |
| Plan Check Approved | 1/13/2026 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/16/2026 | SERGIO GUTIERREZ |
| Issued | 1/16/2026 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 11/14/2025 | JASON CHAN |
| CPC | Cleared | 11/14/2025 | JASON CHAN |
| Address approval | Cleared | 11/18/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 11/18/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 11/18/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 11/18/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 11/18/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 11/18/2025 | JESUS CISNEROS |
| Hydrant and Access approval | Cleared | 11/18/2025 | JOHN CONNEALLY |
| Permit | Cleared | 11/18/2025 | JESUS CISNEROS |
| Street Frontage | Cleared | 11/18/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 11/19/2025 | JESUS CISNEROS |
| Community Plan Implem. Overlay | Cleared | 11/26/2025 | EDER ROMERO |
| Roof/Waste drainage to street | Cleared | 12/1/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | JESUS CISNEROS |
| Zoning Plan Check | Cleared | 12/18/2025 | KAITA SAITO |
| GPI Written Notices | Cleared | 1/13/2026 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 1/13/2026 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Frisby,, Cuyler Sean; Lic. No.: C86179 | 68 S RIVER VIEW CIR LEHI, UT 84043 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/9/2026 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 2/9/2026 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/13/2026 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/27/2026 | Approved | RYAN SALAZAR |
| Deputy Steel/Welding | 3/18/2026 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/28/2026 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/4/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 5/5/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/5/2026 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/14/2026 | Partial Approval | WILBER ROSALES |
| Shower Pan | 5/14/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 5/20/2026 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 5/26/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/1/2026 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 6/1/2026 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/1/2026 | Approved | KIRK SANDERS |
| Structural Steel Frame | 6/1/2026 | Corrections Issued | KIRK SANDERS |
| Insulation | 6/5/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/12/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/12/2026 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 6/12/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/15/2026 | Approved | KIRK SANDERS |