1331 W LAS FLORES DR 90041
Certificate Information: 1331 W LAS FLORES DR 90041
- Application / Permit
- 25014-10000-04618
- Plan Check / Job No.
- B25LA43437
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT (E) DETACHED GARAGE WITH ADDITION TO AN UNPERMITTED ACCESSORY DWELLING UNIT PER P/BC 2023-150. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 4/20/2026
- Issuing Office
- Current Status
- Issued on 4/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2025 | KAMYAR EMAMI |
| Corrections Issued | 11/22/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 3/11/2026 | KAMYAR EMAMI |
| Applicant returned to address corrections | 4/1/2026 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/6/2026 | ALEC MOUSAKHANIAN |
| Issued | 4/20/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2026 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 1/9/2026 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 1/15/2026 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 3/9/2026 | RAMAZANALI ALMASI |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2026 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: NA88029 | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/2/2026 | Approved | DANIEL DELACRUZ |
| Special/Order Compliance | 6/9/2026 | Approved | DANIEL DELACRUZ |
| Pre-Inspection | 6/17/2026 | Not Ready for Inspection | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 7/14/2026 | Approved | DANIEL DELACRUZ |