4211 W DUNDEE DR 90027
Certificate Information: 4211 W DUNDEE DR 90027
- Application / Permit
- 25014-10000-04512
- Plan Check / Job No.
- B25LA42321
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert (e) detached garage with addition into 2- story ADU with roof deck per City ordinance. WORK DONE PER ENGINEER DESIGN AND SOIL REPORT. "COMPLY WITH DEPARTMENT ORDER effective date 08/08/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" **13D SPRINKLER REQUIRED**
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2025 | KHUONG TRUONG |
| Assigned to Zoning Architect | 10/16/2025 | CAMERON JONES |
| Corrections Issued | 10/20/2025 | KHUONG TRUONG |
| Quality Review Completed | 10/27/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 11/17/2025 | KHUONG TRUONG |
| Plan Check Approved | 11/25/2025 | KHUONG TRUONG |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/29/2025 | GILBERT URREA |
| Address approval | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| Street Frontage | Cleared | 11/12/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/13/2025 | BIAINA HARITUNIAN |
| Zoning Plan Check | Cleared | 11/13/2025 | CAMERON JONES |
| Grading Pre-Inspection | Cleared | 11/25/2025 | KHUONG TRUONG |
Contact Information
| Architect | Michlig,, Reiko; Lic. No.: NA41097 | , |
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 1/22/2026 | Approved | JOEL ORDAZ |
| Piling/Pier/Caisson | 1/22/2026 | Approved | JOEL ORDAZ |
| Deputy Reinf. Concrete | 1/26/2026 | Approved | JOEL ORDAZ |
| Deputy Drilled-In Anchors | 2/10/2026 | Approved | JOEL ORDAZ |
| Excavation/Setback/Form/Re-Bar | 2/11/2026 | Approved | JOEL ORDAZ |
| PLUMBING-Rough | 2/19/2026 | Corrections Issued | JOEL ORDAZ |
| Deputy Drilled-In Anchors | 2/24/2026 | Partial Approval | JOEL ORDAZ |
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Approved | JOEL ORDAZ |
| Footing/Foundation/Slab | 2/25/2026 | Approved | JOEL ORDAZ |
| PLUMBING-Rough | 2/25/2026 | Approved | JOEL ORDAZ |
| Deputy Steel/Welding | 3/5/2026 | Approved | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Approved | JOEL ORDAZ |
| Deputy Wood Construction | 4/8/2026 | Conditional Approval | PTOLEMY HILL |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Approved | JOEL ORDAZ |
| PLUMBING-Rough | 5/1/2026 | Approved | JOEL ORDAZ |
| BUILDING-Rough-Frame | 5/13/2026 | Corrections Issued | JOEL ORDAZ |
| ELECTRICAL-Rough | 5/13/2026 | Approved | JOEL ORDAZ |
| Green Building Rough | 5/13/2026 | Not Ready for Inspection | JOEL ORDAZ |
| HVAC-Rough | 5/13/2026 | Approved | JOEL ORDAZ |
| Special/Order Compliance | 5/13/2026 | Corrections Issued | JOEL ORDAZ |
| Verify Sprinkler Sign Off | 5/13/2026 | Corrections Issued | JOEL ORDAZ |