7806 S MIDFIELD AVE 90045
Certificate Information: 7806 S MIDFIELD AVE 90045
- Application / Permit
- 25014-10000-04511
- Plan Check / Job No.
- B25LA42319
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ADDITION TO (E) SFD TO ENLARGE BEDROOM. ENCLOSE (E) SUNSHELTER TO CREATE A DINING ROOM. INTERIOR REMODEL OF (E) SFD.
- Permit Issued
- Issued on 1/28/2026
- Issuing Office
- Valley
- Current Status
- Issued on 1/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2025 | JONATHAN PLATERO |
| Corrections Issued | 10/16/2025 | JONATHAN PLATERO |
| Building Plans Picked Up | 10/17/2025 | APPLICANT |
| Applicant returned to address corrections | 1/15/2026 | KAMYAR EMAMI |
| Plan Check Approved | 1/22/2026 | KAMYAR EMAMI |
| Issued | 1/28/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/2/2026 | TONY CHIANG |
| Grading Pre-Inspection | Cleared | 1/9/2026 | GERMAN RODRIGUEZ MENDOZA |
| Specific Plan | Cleared | 1/20/2026 | HAMID GHAEMMAGHAMI |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2026 | TONY CHIANG |
Contact Information
| Contractor | Barrington Construction And Remodeling Inc; Lic. No.: 1123822-B | 2977 CALLE ESTEPA THOUSAND OAKS, CA 91360 |
| Engineer | Danialian,, Derik; Lic. No.: C94256 | 15904 INDEX ST. GRANADA HILLS, CA 91344 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/4/2026 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 2/4/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Partial Approval | ANTHONY EGSON |
| Insulation | 2/10/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 2/10/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 4/10/2026 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/10/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/15/2026 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/5/2026 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 5/5/2026 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 5/5/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 5/5/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/5/2026 | Approved | JESUS PINEDA |
| Insulation | 5/12/2026 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 5/15/2026 | Approved | MICHAEL LEWIS |