3823 W EDENHURST AVE 90039
Certificate Information: 3823 W EDENHURST AVE 90039
- Application / Permit
- 25014-10000-04417
- Plan Check / Job No.
- B25LA41198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED TRELLIS
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/7/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 10/9/2025 | APPLICANT |
| Applicant returned to address corrections | 10/31/2025 | DANIEL YIP |
| Issued | 10/31/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | NICHOLAS LOPEZ |
| No Progress | 3/9/2026 | DEROLD HAUFF |
| CofO in Progress | 3/9/2026 | DEROLD HAUFF |
| Permit Finaled | 3/9/2026 | DEROLD HAUFF |
| CofO Issued | 3/9/2026 | DEROLD HAUFF |
| Permit Finaled | 3/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2025 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 10/31/2025 | ROSE STEIN-WENDT |
| Supp. Use District POD/CDO/TDO | Cleared | 10/31/2025 | DAVID URITA |
Contact Information
| Contractor | Tarte Design Build Llc; Lic. No.: 1120612-B | 1557 SILVERWOOD TERRACE LOS ANGELES, CA 90026 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 11/10/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 12/10/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 12/10/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 12/10/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/12/2025 | Partial Approval | RONNIE MEDINA |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 1/13/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 1/13/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 1/13/2026 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 1/13/2026 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 1/15/2026 | Approved | NICHOLAS LOPEZ |
| Final | 3/4/2026 | OK to Issue CofO | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/4/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 3/4/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 3/4/2026 | Approved | NICHOLAS LOPEZ |