135 S LA JOLLA AVE 90048
Certificate Information: 135 S LA JOLLA AVE 90048
- Application / Permit
- 25014-10000-04414
- Plan Check / Job No.
- B25LA41124
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage to ADU plus addition PER GC 66323(a)(1)
- Permit Issued
- Issued on 1/30/2026
- Issuing Office
- Current Status
- CofO in Progress on 6/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2025 | SERGIO MUNIZ |
| Corrections Issued | 10/18/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/29/2025 | SERGIO MUNIZ |
| Plan Check Approved | 1/29/2026 | SERGIO MUNIZ |
| Issued | 1/30/2026 | APPLICANT |
| CofO in Progress | 6/10/2026 | ANTHONY EGSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2025 | CELINA MORENO |
| Sewer availability | Cleared | 11/7/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/21/2025 | CELINA MORENO |
| Construction near power lines | Cleared | 12/22/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2026 | Partial Inspection | WILBER ROSALES |
| Deputy Wood Construction | 3/5/2026 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/6/2026 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Rough | 3/6/2026 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Approved | WILBER ROSALES |
| Footing/Foundation/Slab | 3/6/2026 | Approved | WILBER ROSALES |
| HVAC-Rough | 3/6/2026 | Corrections Issued | WILBER ROSALES |
| Interior/Exterior Lathing | 3/6/2026 | Approved | WILBER ROSALES |
| METHANE-Barrier | 3/6/2026 | Approved | WILBER ROSALES |
| METHANE-Subgrade | 3/6/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/6/2026 | Approved | WILBER ROSALES |
| Sewer | 3/6/2026 | Partial Inspection | WILBER ROSALES |
| Drywall Nailing | 3/10/2026 | Approved | WILBER ROSALES |
| Insulation | 3/10/2026 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 5/15/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 5/15/2026 | Approved | WILBER ROSALES |
| Final | 5/15/2026 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/15/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 5/15/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 5/15/2026 | Approved | WILBER ROSALES |
| METHANE-Final | 5/15/2026 | Approved | WILBER ROSALES |
| METHANE-Rough | 5/15/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 5/15/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 5/15/2026 | Approved | WILBER ROSALES |
| Final | 6/9/2026 | OK to Issue CofO | ANTHONY EGSON |