135 S LA JOLLA AVE 90048

Certificate Information: 135 S LA JOLLA AVE 90048

Application / Permit
25014-10000-04414
Plan Check / Job No.
B25LA41124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to ADU plus addition PER GC 66323(a)(1)
Permit Issued
Issued on 1/30/2026
Issuing Office
Current Status
CofO in Progress on 6/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2025 APPLICANT
Assigned to Plan Check Engineer 10/10/2025 SERGIO MUNIZ
Corrections Issued 10/18/2025 SERGIO MUNIZ
Applicant returned to address corrections 12/29/2025 SERGIO MUNIZ
Plan Check Approved 1/29/2026 SERGIO MUNIZ
Issued 1/30/2026 APPLICANT
CofO in Progress 6/10/2026 ANTHONY EGSON

Permit Application Clearance Information

Address approval Cleared 11/1/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/7/2025 CELINA MORENO
Sewer availability Cleared 11/7/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 11/21/2025 CELINA MORENO
Construction near power lines Cleared 12/22/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2026 Partial Inspection WILBER ROSALES
Deputy Wood Construction 3/5/2026 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 3/6/2026 Partial Approval WILBER ROSALES
ELECTRICAL-Rough 3/6/2026 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Approved WILBER ROSALES
Footing/Foundation/Slab 3/6/2026 Approved WILBER ROSALES
HVAC-Rough 3/6/2026 Corrections Issued WILBER ROSALES
Interior/Exterior Lathing 3/6/2026 Approved WILBER ROSALES
METHANE-Barrier 3/6/2026 Approved WILBER ROSALES
METHANE-Subgrade 3/6/2026 Approved WILBER ROSALES
PLUMBING-Rough 3/6/2026 Approved WILBER ROSALES
Sewer 3/6/2026 Partial Inspection WILBER ROSALES
Drywall Nailing 3/10/2026 Approved WILBER ROSALES
Insulation 3/10/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 5/15/2026 Approved WILBER ROSALES
ELECTRICAL-Final 5/15/2026 Approved WILBER ROSALES
Final 5/15/2026 Corrections Issued WILBER ROSALES
Green Building Final 5/15/2026 Approved WILBER ROSALES
Green Building Rough 5/15/2026 Approved WILBER ROSALES
HVAC-Final 5/15/2026 Approved WILBER ROSALES
METHANE-Final 5/15/2026 Approved WILBER ROSALES
METHANE-Rough 5/15/2026 Approved WILBER ROSALES
PLUMBING-Final 5/15/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/15/2026 Approved WILBER ROSALES
Final 6/9/2026 OK to Issue CofO ANTHONY EGSON