640 W 111TH ST 90044
Certificate Information: 640 W 111TH ST 90044
- Application / Permit
- 25014-10000-04403
- Plan Check / Job No.
- B25LA41062
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- conversion of and addition to (E) 1-story detached garage to ADU per GC 66323(a)(2) R3 occupancy
- Permit Issued
- Issued on 11/17/2025
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2025 | KELVIN CHUONG |
| Corrections Issued | 10/4/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 10/16/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/10/2025 | KELVIN CHUONG |
| Plan Check Approved | 11/12/2025 | KELVIN CHUONG |
| Issued | 11/17/2025 | APPLICANT |
| CofO in Progress | 4/1/2026 | BEN MOLSTAD |
| Permit Finaled | 4/2/2026 | ANSON MAGLASANG |
| CofO Issued | 4/2/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/2/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 10/6/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Tech Master Construction Inc; Lic. No.: 1054601-B | , |
| Engineer | Sandoval,, Martin; Lic. No.: NA56905 | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2025 | No Access for Inspection | BEN MOLSTAD |
| Sewer | 12/2/2025 | No Access for Inspection | BEN MOLSTAD |
| Underground Mechanical | 12/2/2025 | No Access for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/8/2025 | Corrections Issued | BEN MOLSTAD |
| Sewer | 12/8/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/10/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | BEN MOLSTAD |
| Sewer | 12/10/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 1/7/2026 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 1/7/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 1/27/2026 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 1/27/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 1/27/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 2/2/2026 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2026 | Approved | BEN MOLSTAD |
| HVAC-Rough | 2/2/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 2/2/2026 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | BEN MOLSTAD |
| Green Building Rough | 2/4/2026 | Approved | BEN MOLSTAD |
| Insulation | 2/4/2026 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/4/2026 | Partial Approval | BEN MOLSTAD |
| Shower Pan | 2/4/2026 | Approved | BEN MOLSTAD |
| Insulation | 2/6/2026 | Approved | BEN MOLSTAD |
| Drywall Nailing | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Gas Test | 3/2/2026 | Approved | BEN MOLSTAD |
| Service/Power Release | 3/2/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 3/11/2026 | Approved | BEN MOLSTAD |
| Service/Power Release | 3/11/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/20/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/20/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/20/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 3/20/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 3/20/2026 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 3/20/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/20/2026 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/27/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/27/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/27/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 3/27/2026 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 3/27/2026 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Not Ready | BEN MOLSTAD |
| ELECTRICAL-Final | 4/1/2026 | Approved | BEN MOLSTAD |
| Final | 4/1/2026 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 4/1/2026 | Approved | BEN MOLSTAD |
| HVAC-Final | 4/1/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 4/1/2026 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | BEN MOLSTAD |