640 W 111TH ST 90044

Certificate Information: 640 W 111TH ST 90044

Application / Permit
25014-10000-04403
Plan Check / Job No.
B25LA41062
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
conversion of and addition to (E) 1-story detached garage to ADU per GC 66323(a)(2) R3 occupancy
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2025 APPLICANT
Assigned to Plan Check Engineer 10/3/2025 KELVIN CHUONG
Corrections Issued 10/4/2025 KELVIN CHUONG
Applicant returned to address corrections 10/16/2025 SAMUEL GONZALEZ
Applicant returned to address corrections 11/10/2025 KELVIN CHUONG
Plan Check Approved 11/12/2025 KELVIN CHUONG
Issued 11/17/2025 APPLICANT
CofO in Progress 4/1/2026 BEN MOLSTAD
Permit Finaled 4/2/2026 ANSON MAGLASANG
CofO Issued 4/2/2026 ANSON MAGLASANG
Permit Finaled 4/2/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/6/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 10/6/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/6/2025 SAFA JAVANMARDI
Sewer availability Cleared 10/6/2025 SAFA JAVANMARDI

Contact Information

Contractor Tech Master Construction Inc; Lic. No.: 1054601-B       ,
Engineer Sandoval,, Martin; Lic. No.: NA56905       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2025 No Access for Inspection BEN MOLSTAD
Sewer 12/2/2025 No Access for Inspection BEN MOLSTAD
Underground Mechanical 12/2/2025 No Access for Inspection BEN MOLSTAD
Footing/Foundation/Slab 12/8/2025 Corrections Issued BEN MOLSTAD
Sewer 12/8/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 12/10/2025 Approved BEN MOLSTAD
PLUMBING-Rough 12/10/2025 Partial Approval BEN MOLSTAD
Sewer 12/10/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/29/2025 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 1/7/2026 Corrections Issued BEN MOLSTAD
Wood Frame 1/7/2026 Not Ready for Inspection BEN MOLSTAD
Gas Test 1/27/2026 Partial Approval BEN MOLSTAD
HVAC-Rough 1/27/2026 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 1/27/2026 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 2/2/2026 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Approved BEN MOLSTAD
HVAC-Rough 2/2/2026 Approved BEN MOLSTAD
PLUMBING-Rough 2/2/2026 Approved BEN MOLSTAD
BUILDING-Rough-Frame 2/4/2026 Approved BEN MOLSTAD
Green Building Rough 2/4/2026 Approved BEN MOLSTAD
Insulation 2/4/2026 Corrections Issued BEN MOLSTAD
Interior/Exterior Lathing 2/4/2026 Partial Approval BEN MOLSTAD
Shower Pan 2/4/2026 Approved BEN MOLSTAD
Insulation 2/6/2026 Approved BEN MOLSTAD
Drywall Nailing 2/10/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 2/10/2026 Approved ARTHUR NEGRETE
Gas Test 3/2/2026 Approved BEN MOLSTAD
Service/Power Release 3/2/2026 Not Ready for Inspection BEN MOLSTAD
Gas Test 3/11/2026 Approved BEN MOLSTAD
Service/Power Release 3/11/2026 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 3/19/2026 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 3/20/2026 Corrections Issued BEN MOLSTAD
Final 3/20/2026 Corrections Issued BEN MOLSTAD
Green Building Final 3/20/2026 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 3/20/2026 Corrections Issued BEN MOLSTAD
PLUMBING-Final 3/20/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 3/20/2026 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 3/20/2026 Approved BEN MOLSTAD
ELECTRICAL-Final 3/27/2026 Corrections Issued BEN MOLSTAD
Final 3/27/2026 Corrections Issued BEN MOLSTAD
Green Building Final 3/27/2026 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 3/27/2026 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 3/27/2026 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Not Ready BEN MOLSTAD
ELECTRICAL-Final 4/1/2026 Approved BEN MOLSTAD
Final 4/1/2026 OK to Issue CofO BEN MOLSTAD
Green Building Final 4/1/2026 Approved BEN MOLSTAD
HVAC-Final 4/1/2026 Approved BEN MOLSTAD
PLUMBING-Final 4/1/2026 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved BEN MOLSTAD