2038 W 41ST PL 90062

Certificate Information: 2038 W 41ST PL 90062

Application / Permit
25014-10000-04334
Plan Check / Job No.
B25LA40436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Convert and addition to existing detached garage into ADU per GC 66323 (a)(2).
Permit Issued
Issued on 2/2/2026
Issuing Office
Current Status
Issued on 2/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2025 APPLICANT
Assigned to Plan Check Engineer 9/29/2025 YILE TIAN
Corrections Issued 9/30/2025 YILE TIAN
Applicant returned to address corrections 1/21/2026 DANIEL YIP
Plan Check Approved 1/26/2026 DANIEL YIP
Issued 2/2/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/2/2025 JEFF LOREDO
Roof/Waste drainage to street Cleared 10/20/2025 JEFF LOREDO
Construction near power lines Cleared 12/17/2025 RIDWAN HARDY
Construction within easement Cleared 12/17/2025 RIDWAN HARDY
Sewer availability Cleared 1/2/2026 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 1/7/2026 JEFF LOREDO

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21731 VENTURA BLVD #110      WOODLAND HILLS, CA 91364
Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Ind Construction Llc; Lic. No.: 937833-B       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/12/2026 Approved MICHAEL LEWIS
Footing/Foundation/Slab 3/16/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Corrections Issued SABAS ALONSO
Deputy Wood Construction 4/20/2026 Conditional Approval GEM DE OCAMPO
ELECTRICAL-Rough 4/28/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Approved SABAS ALONSO
HVAC-Rough 4/28/2026 Approved SABAS ALONSO
PLUMBING-Rough 4/28/2026 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/4/2026 Approved SABAS ALONSO
Green Building Rough 5/4/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 5/4/2026 Partial Approval SABAS ALONSO
Shower Pan 5/4/2026 Not Ready for Inspection SABAS ALONSO
Insulation 5/8/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 5/8/2026 Approved SABAS ALONSO
Shower Pan 5/8/2026 Corrections Issued SABAS ALONSO
Drywall Nailing 5/12/2026 Approved SABAS ALONSO
ELECTRICAL-Rough 5/18/2026 Approved RONNIE MINDANAO
Sewer 5/18/2026 Approved RONNIE MINDANAO
Shower Pan 5/18/2026 Approved RONNIE MINDANAO
Underground Mechanical 5/18/2026 Corrections Issued RONNIE MINDANAO
Underground Mechanical 5/21/2026 Corrections Issued BRENDAN MORELLI
Underground Mechanical 5/27/2026 Corrections Issued BRENDAN MORELLI
Underground Mechanical 5/29/2026 Approved SABAS ALONSO