611 N STANLEY AVE 90036
Certificate Information: 611 N STANLEY AVE 90036
- Application / Permit
- 25014-10000-04276
- Plan Check / Job No.
- B25LA39975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Addition and Remodel to (E) Single Family Dwelling. NFPA 13D sprinkler provided
- Permit Issued
- Issued on 1/16/2026
- Issuing Office
- Current Status
- Issued on 1/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2025 | ALFREDO JARA |
| Corrections Issued | 9/30/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 12/15/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 12/25/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 1/12/2026 | JOHNPAUL ISIP |
| Plan Check Approved | 1/14/2026 | KAVIAN REFAHI |
| Issued | 1/16/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 10/6/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2025 | JEFF LOREDO |
Contact Information
| Contractor | Davidi Construction Inc; Lic. No.: 1107121-B | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 2/13/2026 | Not Ready for Inspection | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2026 | Partial Approval | JOSH MEISTER |
| PLUMBING-Rough | 2/20/2026 | Corrections Issued | JOSH MEISTER |
| Special/Order Compliance | 2/20/2026 | Partial Inspection | JOSH MEISTER |
| Underground Mechanical | 2/20/2026 | Partial Inspection | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2026 | Conditional Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 4/1/2026 | Corrections Issued | JOSH MEISTER |
| Sewer | 4/1/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 4/3/2026 | Approved | JOSH MEISTER |
| HVAC-Rough | 4/7/2026 | Not Ready for Inspection | JOSH MEISTER |
| Underground Mechanical | 4/7/2026 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Rough | 4/8/2026 | Approved | JOSH MEISTER |
| Underground Mechanical | 4/8/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 4/10/2026 | Approved | JOSH MEISTER |
| Underground Mechanical | 4/10/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 4/14/2026 | Approved | JOSH MEISTER |
| HVAC-Rough | 4/14/2026 | Approved | JOSH MEISTER |
| Underground Mechanical | 4/14/2026 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/23/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 4/23/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 4/23/2026 | Partial Approval | JOSH MEISTER |
| METHANE-Rough | 4/23/2026 | Approved | JOSH MEISTER |
| Wood Frame | 4/23/2026 | Approved | JOSH MEISTER |
| Wood Frame | 4/24/2026 | Approved | JOSH MEISTER |
| Insulation | 4/28/2026 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 5/4/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 5/4/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Shower Pan | 5/4/2026 | Approved | GEM DE OCAMPO |
| Insulation | 5/6/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 5/6/2026 | Approved | JOSH MEISTER |
| Shower Pan | 5/6/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 6/4/2026 | Approved | JOSH MEISTER |