926 N ILIFF ST 90272
Certificate Information: 926 N ILIFF ST 90272
- Application / Permit
- 25014-10000-04253
- Plan Check / Job No.
- B25LA39664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 10/30/2025
- Issuing Office
- Current Status
- Issued on 10/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | JOE VO |
| Corrections Issued | 9/30/2025 | JOE VO |
| Quality Review Completed | 10/3/2025 | GARO TELMI |
| Plan Check Approved | 10/28/2025 | JOE VO |
| Issued | 10/30/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 9/29/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/29/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 10/14/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 10/23/2025 | KURT CORRAL |
| GPI Written Notices | Cleared | 10/28/2025 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/5/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/6/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 12/17/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Partial Inspection | TEMISTOCLES CAAL |
| Sewer | 1/30/2026 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/30/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 3/4/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2026 | Partial Approval | TEMISTOCLES CAAL |
| Final | 3/12/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/13/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/19/2026 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 3/19/2026 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 4/2/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 4/2/2026 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/2/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/15/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Insulation | 4/24/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 4/29/2026 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 5/1/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/8/2026 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 5/12/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/12/2026 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 5/28/2026 | Approved | JESUS PINEDA |